US Army Corps of Engineers Office of the Chief of Engineers BISON EP 415·1·4 31 Aug 86 Network Analysis Systems Guide Uf\JiVERSrrY l\TBtJFFAL·~.J - ~\UCl 0 5 lS93 DOCLJiVJcJ\: lti UEPOSiTOHY LIBR;J~RY 04:1:3 DAEN-ECC-Q DEPARIMENr OF THE ARMY U.S. Army Corps of Engineers Washington D.C. 20314 EP 415-1-4 E'hanplet No. 415-1-4 31 Au gust 1986 Construction NE'IWORK ANALYSIS SYSTEMS GUIDE FOREWORD This guide provides information for Corps of Engineers Construction and Eilgineering personnel in the application of Network Analysis Systems. It is intended to give a basic introduction to the two diagraning systems, arrow diagrBDing and precedence diagraning, and to instruct the reader in the various potential management uses of Network Analysis both when scheduling and when updating the schedule to show progress. '!he information g1ven in this phamplet replaces the Network Analysis 3,ystems Guide formerly included in ER 1-1-11 at Appendix A in the 1 March 1973 edition of the ER. Basic policy and procedure concerning the use of Network Analysis are contained in the most current edition of ER 1-1-11. While most Network Analysis scheduling systems encountered in the field will fall in either of the two diagraning techniques described herein, there systems available all of which have differing characteristics. are numerous Some managers will find certain systems preferable to others. For a more detailed discussion of the systems available and instruction in the use and capabilities of Network Analysis, the Network Analysis System course, TlMNAS is offered several times annually at various locations foreign and domestic. FOR THE C Sto,ooo 1 OUTSIDE PLUMBING I (45) t7,000 I 125 SUB S APP SH OWGS OUTSIDE ELEC 8 PLUMB OU"f'SIOE ELECTRICAL (4~) 190) $24,000 I I SUBMIT MISC BLDG EQUIP GOv'r APPROV MISC dLOG EQUIP I 1301 1201 / suBMIT HOSPITAL a MtSC EQUIP GOV'T APPROV HOSP 6 MISC EQUIPI (45) (3()! ISUBMIT SH OWGS GOV' T APPROV CASEWORK (45) (30) SUBMIT RESILIENT FLOOR SAMPlES ·Gav'r APPROV 8 COLOR SEL RESILIENT FLOOR 1301 (30) SUBMIT SH OWGS MILLWORK GOV'T APPROV MILL WORK no> (201 SUBMIT GOV 'r APPROV COLOR SEL VINYL WALL COVERING 1301 (3Q) SUBMIT PAINT SAMPLES GOV'T TEST 6 APPROV PAINT 130) (30) S~SMIT 8 APPAOV CANOPIES 8 SIGNS DOOR CANOPIES 6 SIGNS (451 2,000 218 ELECT 1631 114 SUBMIT X RAY PROT[ C T ION 211 MECH 6 PLUMB 1 t3o\ !70) I SUBMIT ROOF" 8 SHEETMETAL SHOP OWGS GQV'T APPROV K-RAY PROTECT DELIVER PROTECT MAlLS (301 !201 (75) 3,~00 -.1'/] 31 Gov·r SHMTL SH OWGS 6 ROOF" 100~ ~ 1 6~~Sa R~~:F" ~~L ..t5' SUBMIT DECK SH DWGS DELIVER ROOF" 135) (30) GRADE BEAMS CONC CONC " 115) 1301 l10.000 (18) MISC METALS BSMT STEPS a LNOGS s 3,500 1101 sgoo ffi NT~ I ,,, FORMS APPROV PAN FORMS FORMS SU8 SH OWGS METAL DOOR BUCKS GOV'T APPROV MTL OR F"AB 8 DELIVER MTL DR BUCKS (15) (201 1901 sz.ooo SUB SH OWGS STRUCT STL a JOISTS GOV'T APPRO\' STR STL 6 JSTS FAB a DEL STL COLS (301 (20) (45) $1,500 F"AB a DEL STR fl JSTS 190) 19,000 (30\ ,. SUB 8 APPROV MASONRY MATLS MATLS SAMPLE MASONRY PANELS (45) 1"9,500 121 SUe SH OWGS MTL WINDOWS M T L WINDOWS FAe 5 DELIVER METAL WINDOWS !3D) (901 S2,0DO Sue LIST 5 SAMPLES BLDRS HARDWARE HARDWARE DELIVER BLDRS HARDWARE (30) (120) $9,000 SUB SH OWGS ALUM ENTR 5 MTL DOORS ALUM ENTR a loiTL DOORS ALUM ENTR 8 MTL DRS " 145) "" 4,500 sue LATH a GOV'T APPROV LATH 8 PLASTER MAlLS a PLASTER (451 115) SUB CERAMIC TIL[ TILE 8 COLOR SEL DELIVER CERAMIC (45) 145) SUBMIT TOILET PARTITIONS Ito ACCESSORIES GOV'T APPROV TOIL PART a ACCES "' (451 (20) SUB loll T ~LUMI!I a MECH a rout~ PLUMB a MECH F"IXT a EQUIP ( ~0) '" SUI!IMIT ELECT F"IXT & [QUIP GOV'T APPROV ELECT F"IXT 8 EQUIP 1301 (301 EP 415-1-4 31 Aug 88 '" SLJeGRADE AND <'><' ~.,."1 BASE F'QR PAVING J 6 -."> , ... .,, • 't ......... 2"' "'-'''t." ,.,, ·~ ......... 'I' (I TI~=~OIL 8 F"INE --7;""'/"'~0"'I~~G---------, --'.\ ---'\ I DELIVER HOSPITAL 8 Ml~ EQUIP\ 11801 43,00D \ DELIVER CASEWORK I 11~01 '16 ,0 00 DEL~VER RESILIENT F'LOOR MATL 14~) '3.~00 I I F'A8 11~01 a DELIVER MILLWORK 16,000 DELIVER 160) COVER 1,~00 DELIVER 14~1 MATLS UGH IN 2,0,000 g., INSTALL PO) a SIGNS $ ~00 ROUGH -IN 2,1,000 I •z& '•o "' ••• CERAMIC TILE (221 14.500 FINAL SUBMISSION ANALYSIS SOLUTION DELIVER TOILET PART AND ACCESS 1901 I4,000 MONTEDON CONSTRUCTION CO. CONTRACT NO 999 DELIVER PLUMB a MECH [QUIP a F'I)(T !150) '4',000 DISPENSARY LACKLAND AFB, TEXAS DELIVER ELECT a EQUIP 11201 I23.ooo SUBMITTED BY ~ OAT£ /f~T6" ~ RECOMMENDED 8Y ~t8~,,1)..,.~. DATE ~_.P-? 76 APPROVED BT _,A, :Jtft'$-,c;._..{ tfJ# DATE J4.f1-1Jr .?6 FIGURE 28 - • 11\"4 PIWJt=CT CONTROL SYSTEM RUil DA TF Jill 7b S C H E 0 II L E A f P 0 A T OATA !'ATE JUL 7ft * * * * RIJil SEfllllNCE 0 NlltJIIRK 10 Ill OA OISP£1\JSARY•LACKLAI~O AFA TIC '40NHOIIN CONSR FROM JUL 76 TO 141 AUG 77 SEfliiENCF I•J PAiif TOT S T A R T START F I N I S H FIN ( I l (J) U l S C H 1 P T I 0 ~ IIUPAT CAL FARLY LATE FLOAT fAALY LIT[ FLOAT 5 NTP 1.0 71 1JIIL7b l Jill 71> 0.0 lJliL7b lJUL76 o.o ") 10 "'0H ~ LAYIIIIT 7.0 71 ZJIIL 7& ;>7.11JI. 7& zs.o 8Jlll 7& 2AUG7fl 25.0 'i 20 SIIR ~ APP "4lCH ~ fLU:l ~OUt;H•IN MTLS 30.0 71 ?JIIL7b 3.1111. 7& 1.0 31JIIL 7& UUG76 1.0 ., 'i Z5 SUK SH O~GS PA~ F~R~S i'O.O 71 ?JIIL7h I 7AIJ(;7f) 411> 0 0 c?lJUL7& 5SEP7& 11&.0 ~(I SIIR SH li',.r;S "1[ TAL lllJIIII HIICII S i.'O.O 71 ?JIIL7b i'i_>AIH~7f> '51 .0 21JliL7& 10SEP76 51.0 "i 3'J SIIR ~HI IJWGS SIRIICT :>TL ~ JOISTS 30.0 71 i'JIIL7b li.'AIIf.7& Q1.0 31JUL7ft 10SEP76 111.0 'j Qfl SIIH ~ AI'PIHIV 'IASONRY MAlLS qo;.o 11 ZJIIL7h ;>c;nr.T71> 115.0 l~A~G7& 8DEC76 11'5.0 ") Q'J SUR SH l!WGS Mll WlNlillwS 30.11 71 i'JIIL7b 10SI:.P7b 70.0 31JIIL7& 90CT76 70.0 'j '5o SUR LIST ,o, SAi·IPLfS lllOIIS HAIIO~AHE 50.0 7 I 2JIIL7b I~SI:.P7b 7.?.0 31JIIL7& llOCT76 72.0 ") '5') SIIR SH flvjf,S ALIH~ I:.NTH ~ MTL IJf)OHS 41'5. 0 71 ZJIIL 7b HlC T7h 'H • 0 15 A IIG 7b 20NOV7ft 97.0 0'\ I ., 1>0 SUH I ATH II PLASTfH qc;.o 11 i.'JIIL7f> i''lOHH> l7b.O 1'5AIIG7ft 7FER77 17&.0 \Jl 5 1>'5 SUh CEHAMIC TILl 415.n 71 i'JUL7b 130EC:7& 11>41.0 15AUG7b 26JAN77 1&Q.O ') 70 SIIAMTT TDILFT PAIITITTONS & AfCESSOHIES 41'5.0 71 iJIJL 7b li'FEH77 .?<'5.0 l'5AIIG7ft t'8MAN77 225 0 0 ") 75 SIIRI-IIT PLUMB It "'FCH FIXT t. EfJIITP 30.0 71 i.'JUL7b ?OOfT7b 110.0 31JUL7& l8NOV7ft 110.0 ., II 0 S IIIH'l T ~ U r: T F I X T ~ Htll[ P 30.0 71 ?.JIJL71> 170EC71> 1&8.0 3lJUL7ft l5JAN77 1&8.0 ') 1\'J SU~ It APP 5H UrlbS MISC ~fTALS 41'5.0 71 ?JIIL7b 170CT7~> 1117.0 15AUG7& 30NOV7ft 107.0 c; ~0 SIIR ~ 4PP SH o..r,s Wt:: TNF STL . 3'5.0 71 ?JilL 7b c?.JIIL 7& 0.0 5AUG7& 5AUG7ft o.o c; Q'} SliH'-'lT J\ APPRI)V ROOF 0£1:11 Stl OI'IGS 41'5.0 71 ?JUL7b i.'b0CT7& 11&.0 l5AUG7& 9DEC7ft llf>.O ') I 00 SLIHIH T 1-/0IIF ~ Sti£1:. H~f TAl ~HUP [),;(;S ~0. 0 7 I i.'JIJL7b I\OC:T71> ~8.0 31JIIL 7& 6NOV7& 98.0 Wtz:l 1-''"d 21NOV76 113.0 ~ IO'J S11Ht1TT X·HAY PWIITt:.CTIO~I 30.0 11 i.'JIIL7b i.'50CT71> 113.0 31JUL7b :x> (::: ~ 2&7.0 l'5AUG7b ~lo4AY77 267 0 0 'i 110 511HtHT"' ~PPRUV iltlOJ.I ca·~IIPTES It SIGNS 415.0 71 2JIIL7b i'f>MAR77 ()Q ,_. Ln COl 0'\ ,_. I ~ FIGURE 29 :!. SEQUENCE 1-J PAGE 2 Wt%3 -----------------------------------------------------------------------------------------------------------------------1-'"tl TOT S T A ~ T START F I N. I S H FIN· (I) (J) D £ S C R I P T I D N OURAT CAL EARL.Y LATF. FLOAT EARLY LATE FLOAT > r:: ~ -----------------------------------------------------------------------------------------------------------------------OQI-' \JI 5 115 SUBMIT PAINT SAMPLES 30.0 71 2JUL7b 19JAN77 201.0 31JULT& 1TFEB7T 201.0 OJI 0\ 1-' I 5 120 SUAM~T VINYL NALL COVERING 30.0 71 2JULTb 22M&R7T 2&3.0 31JtiLTb 20APR17 2t.3.0 ~ 5 125 SUBMIT S~ DwGS ~ILLWORK 30.0 71 l»JUL 7b 25DEC7& 1Tb.O 31JUL7& 23JAN7T 17& 0 0 5 I ~0 SIIBMTT RFSIL lENT FLOOR SAMPLES 30.0 71 2JUL7b 2lFER77 23b.O 31JIIL7& ?4MAA7T 23&.0 5 135 SU~MIT SH Dw~S CASE~ORK 45.0 71 ?JUL7b 27NOV7b 148.0 15AUG7b I OJAN7T 148 0 0 5 1•0 SUBMIT HOSPITAL & ~ISC EnuiP 45.0 71 2JIIL 7b 170CT7b 107 0 0 15AUG7b 30NOV7& 107 • 0 5 145 SU~MIT MISC ALOG EQUIP 30.0 71 ?JUL7b 2MAH77 243.0 31JUL7b 311UA17 243o0 5 150 CONC DES MIX 15.0 71 2JUL 7b nAIIG7b 3'5.0 lbJUL7& 20AUG7& 35.0 5 330 PRE-QUALIFY wELDFRS :n.o 11 2JUL7b 30NOV7b 151.0 31JUL7b 290EC7& 151 0 0 5 bOO SUB .\ APP Sl'i Di'lliS OIJTS tllE fLfC & PLUMR 45.0 71 ?JUL7b 3NOV7b 124.0 15AUGTb 170EC7& 124.0 10 I '::1 ROllliH G~AO & £XC IV KL QG 14.0 71 9JUL 7b ]AUG76 <'5.0 22JUL7b 1bAUG7b 25.0 10 b05 OtHOL ~ SIT£ GRADING H.O 71 9JUL7b 31DEC7& 175.0 9AUG7b 31JAN17 17'3.0 15 15') R o.o 71 22JUL7b lbAIIG7b 25 • 0 22JUL 1& 1UIJG7& 2'5.0 0\ 15 .?.b5 R o.o 71 2?JIIL7b i'OIUG7b 29.0 22JUL7& 20AUG7& 29.0 I 0\ 20 155 OEL MECH ~ ELECT ~OUGH-IN MTLS INITIAL 1'i.l) 71 IAUG76 2AIIr.7b 1.0 15AUG7b 1&AIJG7& 1.0 25 lbO GOV'T &PPROV PIN FORMS 1'i.O 71 2?JIIL 76 bSEP7b 4& 0 0 5AUG7b 20SEP7b 4b.O 30 lb'5 GOV' T 4PPiiOV tHL llR RiiCKS 1"i.O 71 i.2JUL 7& 11SEP7b 51.0 5AUG7& 25SEP7& 51.0 3'5 170 GOV'T &PP~Ov STR STL ~JSTS 20.11 71 IAIJI>7b 1!SEP7b 41.0 20AIIG7b 30SEP7& 41.0 40 17') OlLIVER ~ASUNRY MAlLS 4'i.O 71 lbAIIG7b qoF.C7b 115.o zqsEP7t. 22JAN7T 115.0 4'5 180 ~lJV'T APP~OV IHL o'IJ;WQWS zo.o 71 UUG76 100CT7& 70.0 20AUG7b 290CT7b 70.0 '50 1R') GIJV 1 T IPPI.'OV tiL OilS HARlliiAPf 30.0 71 lAUGh I.?.OCT7b 72.0 10AUG7b 10NOV7b 72.0 5'i 1q0 GOV'T IPP~OV ALUM ENTI1 ~ MTL OOORS 211.1) 71 16AUt;7b i'INLIV7b 97.0 4SEP7b IODEC76 en •.o bO lqS GuV'T IPPROV LITH I PLASTEP 15.0 71 II,AIIG7b 8ftH77 17b.O 30AIIG7b 22Ff877 176.0 FIGURE 29 CONT. - S~•Jo1rr1rE 1-J PAGE 3 TOT S T A R T START F I N I S H FIN ( I l 1.1) ll~SCRIPTION lltiRAT CAL EARLY LATF FLOAT EARLY LATE FLOAT --------------~------------------------------------------------------------------------------------------------------- b'> 200 GOV' T APPI l;tiV' T APPidlV TOIL PAIH II Af.CFS 20.0 71 1bAIIG7b 29MAR77 225.0 4SEP7b 75 ?lu f.OV'T Af'Pt{OV I'LII~IJ 6 t~fCH FIXT & ErllliP 30.0 71 1AIIG7b 19NOV7b 110.0 30AUG7& 110 i'l'> t;uv•T API't\OV I:.UCT ~1Xl .\ fiWIP 30.0 71 1AIIG7b 1bJAN77 1~8.0 30AUG7& 115 3!l'> FA!\ A nu IV[R ~ISC f.IFTALS 45.0 71 1 bAIJG7b 10EC7h 107.0 29S£P7b Qo I c;o II[L R[ 1r1F STI 15.0 71 bAUG7b I>AIIf77& 0.0 20AUG7& Q'J 3<;0 ll~LIV[R ~IJOF llfCK MAlLS 30.0 71 1UIIG7b 100EC7& 11&.0 14SEP7b 100 220 l;tJV' T APPiiOV IWOF & SHMTL SH O~GS 1t;.O 71 1AIIG7b 7NUV7& 98.0 t5AUG7& 10'> L'?'l GIJV' T APPIWV X-IUY l'llOTECT 20.0 71 uur. 1 b 22NUV7b 113.0 20AUG7& 1l«l '.'>00 lltl 1Vt ~ lluOR CAf~OPIES .\ SllitiS 75.0 71 1bAUG7b l0MAY77 2&7.0 290CT7b 0\ ll'l ?10 GOV'T TUH 1', APPROV PAHIT 30.0 71 1AIIG7b l~FER77 201.0 30AUG7& I ...... 120 21'> GIIV' T APPIW\1 COLO~ SFL VII~YL ~~ALL COVERINf. 30.0 71 UIIG7b 2tAPR77 2&3.0 30AUG7& 1?'1 240 GOV'T APPROV MILL~ORK 20.0 71 UIJG7b 24JAN77 17&.0 20AUG7& 130 24'> GOV'T APPROV .\ COLOR SEL RFSILII:.NT FLOOR 30.0 71 1AilG7b 2'l~AR77 23&.0 30AUG7& 13'1 25o GUV'T -PPkllV C4SE~ORK 30.0 71 1bAUG7b 11JAN77 148.0 14SEP7& 140 255 r.ov' T APPIWV HOSP A "I SC [QIJIP 30.0 71 1bAUG7b 1DEC7& 107.0 t0SEP7b 145 ?hO GOV'T APPkOV ~ISC ~LOG E~UIP 20.0 71 UIJG7& tAPR77 243.0 20AUG7& 150 21>'> R o.n 71 20Aill;7b 20AIJG7& 0.0 20AUG7& 150 27~ ~ o.o 71 20AIIG7b 2&AIIG7& boO 20AUG7b 1'50 1>11) ~ o.o 71 20AIIG7b 2MAR77 194.0 20AUG7& 1'5'.'> 27':l f.IOIIf.H-liJ I.INOFR I ~ .::- OQ ...... I.J1 001 0'11-< I .::- ---~-- .-- SEfliiENC:F 1-J PAGE • ----------------------------------------------------------------------------------------------------------------------(I) ( J) 0 E S C R I P T I 0 N TOT DURAl CAL S T A R T EARLY LATE START F I N I S H FLOAT EARLY LATE FIN FLOAT ----------------------------------------------------------------------------------------------------------------------170 170 175 160 3?5 FAR ~ OEL STL COLS 330 FAB ~ OEL STR STL ~ JSTS 335 SAMPLE MASONRY PANELS 3b0 FAR ~ OELIVER METAL ~INOO~S 45.0 71 CJO.O 71 z.o 71 qo.o 11 ZIAIJG7& i!IAUG7& ~OSEP7& ZIAIIG7& IONOV7b 111.0 •OCT7& 10CT7b 41.0 111NOV7& Z3JAN77 11'5.0 10CT7& 300CT7& 70.0 IIINOV7& l11DEC76 81.0 l9DEC7& 41.0 i!4JAN77 115.0 l7JAN77 70.0 Wt'l I-' t-el >c ~ OQ ....... Vl 001 (j\ ....... I ~ 165 345 DtLIVER RLORS HARO~ARE 120.0 71 3UIJG7& 11NOV7& 7i!.O i!IIOEC7b 10MAR77 72.0 1QO ~45 FAR ~ OEL ALUM ftJTR & MTL ORS QO.O 71 5SEP7b 11DEC76 97.0 3DEC76 10MAR77 97.0 IQ5 3~5 DELIVER LATH & PLASTfR MAlLS ~o.o 71 31AUG7& Z3FEB77 17&.0 Z9SEP76 i!4MAR77 17&.0 zoo 405 DELIVER CERAMIC TILE MATLS 4'5.0 71 J5SEP7b ZbFER77 1b4.0 i!90CT7& 11APR77 1&11.0 zoo; 4?'5 OEI.JVER Tlllli:T PART A ACCESS QO.O 7t 5SEP7b 16APR77 i!Z5.0 30EC7& I&JUL77 225.0 ZIO 440 'lfLIVEH PLIJ.,Fl & MlCH EQIIIP & FIXT 150.0 71 31AliG7& lQD£C7b 110.0 Z7JAN77 17MAY17 110.0 Zl5 qo;o DELIVER ELFCT FIXT A [QuiP lZO.O 71 31AUG7& 15FER77 166.0 ZIIOEC7& 14JUN77 1&11.0 zzo 3'5') FAR & lltLIV SHMTL & HOOF ~>o.o 11 1bAIJG7b ZZNOV7b Q8.0 1IIOCT76 lOJAN77 98.0 U5 370 IIELIVEH PROTECT MATLS 75.0 71 ZIAUG7& IZOEC7& 113.0 3NOV7b i!4FE877 113.0 0\ I 00 Z30 Z35 4lO 4~0 DELIVER OEL IVE~ PAINT VINYL MAlLS WALL COVEHING 415.0 bO.O 71 71 3UIIG7b 31AUG7& ZOMAR77 Z1MAY77 Z01.0 i!b].O 1110CT76 i!90CT7& 3MAY77 19Jul77 i!O 1. 0 i!&J.o Z40 4h~ FAA~ Ofl[VER MILLWORK 1ZO.O 71 ZIAIJG7& 1~FEB77 176.0 18DEC7& li!JUN77 17&.0 Z45 470 OELIVER RESILIENT FLOOR MAlL 4'5.0 71 3UUG7b Z4APR77 Z3b.O I•OCT7b TJIJN77 i!Jb • 0 Z50 4~5 OI:.LIVfR CASEwORK 1'50.0 71 15SEP7& 10FER77 1411.0 11FE877 9JUL77 148.0 Z55 4CJO OI:.LIVER HOSPITAL 1!, 'HSC EQUIP 160.0 71 15SEP7b 310EC76 107.0 13MAR77 i!8JUN77 107 .o Z&o 4'l'5 OE.l.IVER MlSC lllflG ffliJ)P QO.O 71 ZIAUG7b ?1APR77 Z43.0 18NOV7b UJUL77 243.0 Zbo; ?70 FTGS & PLINTHS 1b.O 71 ZIAUG7& Z1AUG7b 0.0 5SfP7& 5SEP76 o.o no 300 li~ADF H[AI~~ 30.o 11 &SEP7& bSEP7f> 0.0 50CT7& 50CT7b o.o Z75 Z~~ RA~MT FNO, SLAR, OMS 14.0 71 2bAIJG71:> Z7AIJG76 1.0 8SEP7& 9SEP7b 1.0 FIGURE 29 CONT. PAGf 5 JOT S IA W T START f I ~ I S H FIN SE rwE NCE I-J (I) ( J) II [ S C W 1 P T I ll Ill DIJIU f CAL EARLY LA T£ FLOAT EARLY LATE fLOAT 280 2115 3011 300 305 310 31'5 315 320 320 320 320 0\ I \.0 325 33ll 330 33'5 BS 340 340 340 34'i 3':>0 ?8~ 300 305 31 o 135 31~ 320 3?'5 325 370 37S 3q~ :no 33'5 3'50 340 3f>O 34':) 500 b45 385 :S5S 3b'l t\A~HIT WALLS OAMPPkOUFIIIIG R FIJ,K & GRAUE lh~fllR RLOG R~MT SftPS & LIIIOGS :SOX IIUPR FLR MEf.H II tLECT R-1 FPC PAN SLAH~ II PMS 701 IJIIIOH FLR ME(H II f.LfCT R-1 R COIIIC TOPPING FILL FLECT HOUGH-tU MlCH llo PLIIMI\ ROIIGH-1111 EIIFCT STL COLS 1i METAL tiiiCIH~ llo ALII"' frJTI' WOOf OFCK H(l!lfl'Jr. "'StH '"'[l lt.o 7t qsEP7b 10SEP7b 1.0 2•SEP7b !OSEP7b 1.0 o;.o 11 30SEP71> 10CT7b 1.0 IIOCT7~ SOCT7b 1.0 o.o 71 'iOCT7b t4JAN77 101.0 'iOCT7b 14JAN77 101.0 10.0 71 biiC T1b bOCT7b o.o 1SOCT7b 150CT7b o.o 10.0 71 t.OCT7b 1'iJA~77 101.0 150CT71> 24JAN77 101.0 20.0 7f lbOCT7b lb0CT7b 0.0 IINOV7b 4NOV7b o.o so.o 11 'i1110V7b ~NOV7b o.o 2110EC7& 24DEC7b o.o c;o.o 11 'iNOV7b 'iNOV7t. o.o 2110EC7b 240EC7b o.o o.o 71 240fC7b 240EC7b 0.0 2110EC7b' 240t:c7b o.o 18.0 71 Z'iDEC7b 7Ft:R77 44 0 0 11JAN77 24FER77 44.0 &3.0 71 Z'iOEC7b 4FER77 41.0 25FEtH7 7APR77 41.0 70.0 71 Z'iOfC7b ?.RJAN77 34.0 IIMAH77 7APR77 34.0 s.o 71 Z'i0EC7b l50EC7b o.o zqoEc7& 2qOEC7b o.o o.o 71 zqoEC7& 24JAN77 Zb.O 2qOEC7b 24JAN77 2&.0 10.0 71 30DEC7b 300EC7b 0.0 8JAN77 8JAN77 o.o 27.0 71 300EC7b l .?FER 71 114.0 2'iJAN77 1OMAR77 44.0 3.0 71 300fC7b 25JA11177 o?b.O 1JAN77 Z7JAN77 i.>b.O o.o 71 2'iJAN77 IOMAR77 44.0 25JAN77 l014AR77 44.0 o.o 71 2'iJAN77 23JIIL 77 l 7q.0 2'iJAN77 2!JUL77 17q.o o.o 71 2'iJAIII77 24JIJL77 180.0 2'iJAIII77 24JUL 71 180.0 14.0 71 2&JAN77 11MAQ77 1111.0 IIFEKt7 i.>4MAN77 44.0 12.0 71 qJAN77 qJAN77 0.0 20JAN77 20JAN77 o.o Wtxj 1--''"d 21.0 71 Z l JAJ07 21JAN77 0.0 IOFEB77 10FER77 o.o :>r:: ~ OQ ..... IJl CXIJ c-. ..... I +=-- FIGURE 29 CONT. SEQIIfNCE 1-J PAGE ~ -------------~-~------------------------------------------------------------------------------------------------------- I "' 1-' 0 TOT S T A A T STAAT F I N I S H FIN (I) ( J) U l S C A I P T I 0 N DuRAT C-L EARLY LATE FLOAT EARLY LATE FLOAT 365 370 385 lq5 3q0 3q5 3QO ]q'j 40':.i 4lO 41 U 4l0 430 445 425 4 lO 510 1140 44~ 455 h50 450 455 3~0 3b5 3b5 3b5 370 375 385 3qo 390 390 39') 405 410 410 420 420 425 430 430 440 4.40 445 445 INST ~TL wiNOOWS R R AC OUCTwOkK INTEAIO~ PA~TITION R STIICCO ~ ~ PLASTER WALLS C[ ILG SIJSP SYST A ~~~Sill CE~AMIC TILE PLAS CLG ACOUIST & OTHlR CEllltlGS A H TOILET PART A ACCESS R lOX PAINT A FINISH ~ INST NECH [~UlP R R 14.0 71 2JAN17 i'8JAN77 211.0 1'5JAN77 o.o 71 10FEB77 l4FER77 14.0 10FEB77 o.o 71 10FEB77 24MAR77 4&!.0 10FEB77 s~.o 11 11FE877 11FEtl77 0.0 UPfl77 4&!.0 71 11FEB77 2";FER77 14.0 c?4MAA77 0 •. o 71 ~'5Ff877 1-PR77 41.0 2'5FE877 14.0 71 11FEB77 i'SMA~77 42.0 24FE877 o.o 71 l4MAR77 7APfl77 14.0 .?4MAR77 o.o 71 24MAA77 llAP~77 18.0 24MAA77 14.0 71 2'5MAA77 lOAPR77 .?~.0 UPR77 14.0 71 8APR77 8APIH7 0.0 2UPR77 22.0 71 2'5,..AR77 12APfl77 18.0 15APR17 12.0 71 li»AP~77 22AP~77 0.0 1MAY77 3'5.1) 71 22APA77 27APfl77 5.0 2~MAY77 o.o 71 15AP~77 1f>Jill. 71 92 • 0 1 '5APR77 o.o 71 1'5APR77 3"'4Y 71 11!.0 1'5APN77 17.0 71 16lPA77 1 7 Jl)l 77 92.0 c?MAy77 o.o 71 3MAY77 17MAY77 14.0 314AY77 ~8.0 71 4MAY77 QMAY 77 0 0 0 31MAY77 o.o 71 3MAy77 2hJUN77 54.0 ]rdy77 70.0 71 4MAY77 16M4Y77 14 • 0 12 J lJL 77 o.o 71 ]1MAY77 14JIJN77 14.0 3114AY77 o.o 71 .51MAY77 ltd1JN77 2~.0 311'4AY77 10FEII77 24FE1177 i!4MAN77 7APA7 7 7APR77 7APR77 7APfl77 7APR77 I UPR77 314AY77 21APR77 314A y 7 7 ]MAY 7 7 31MAY77 1~JUL77 3MAY77 2AUG77 1714AY77 3JMAY77 .?b.JUN77 ?bJUL 77 14JIJN77 2bJUN77 2~.0 14.0 42.0 o.o 14.0 41.0 42.0 14.0 18.0 211.0 o.o o.o 18.0 s.o 92.0 u.o 92.0 14.0 o.o '54.0 14.0 14.0 i!b.O w t:>l I-'"d > c:: ~ OQ 1-' Vl 00 I 0"1 1-' I ~ FIGL~ 29 C0~7. - 7 PAGE :; f '11 'I I. L ~ I -J TOT S T A R T START F I N I S H FIN (I l rJ' I• f S C R I I' T I 0 rv OIIIUT CAL fAPL Y LA Tf FLOAT EARLY LATE FLOAT 11115 lift() ~ o.o 71 ]1"1AY77 qt,•, I~ o.o 71 ]IMAy77 qqc; 117(1 ~ o.o 71 H~AY77 11115 c,u':l o:;ux rii'IP P•llllT 11. r Irl qo;.o 11 IJIIi\177 11511 ~'ill II•ST (l.fCT F IXT ~ F•JIIIJ.> 42.0 71 1JLIN77 1155 ho:;u I11ST f'I.IIMII & •1t:Ctl Flq JO.O 71 1JUN77 llb(J <;I U VPI Yl "AlL Crl Vf ~ 14.0 71 1JUN77 lib'; II 7 •; I "S T ':1 0 4 " I Ll. •· 011 ~ lf>.O 71 IJllN77 4 711 IIIII) IH Slt FLI< 21.0 71 1JUN77 1175 111111 k o.o 71 1bJIIN77 1175 'ill', (liMP ·-1ILL•.•llHY 1-'klllFCT 3.0 71 2?JIIN77 411':1 'it !1 TriST CASE.-.IlkK 1180 211.0 71 22JUN77 II 'Ill ';1 0 II.ST ti!ISP ~ MI sc Ell•JIP 35.0 71 2i'JllN77 qqc; o:;1 o II:ST '11 :>C Hlf)(, E!lllll-' 111.0 71 ?2JIIN77 '500 "il11 llT on11R C~NOI-'If:, ~ Slt.NS 10.0 71 .!()JAN77 505 ~10 ?uX PAI~T ~ FINISH 18.0 71 1f>JliL 77 510 l>'i') rLFAN-IIP uLnr. 7.0 71 3AllG77 bOO ,.,,~ ntl MAlLS ns ELEC ~ PLII•tA 45.0 71 1f>AllG7t. bO<; hill ~ o.o 71 9AUG7b lqJUL77 49.0 Jllo4AY77 I IIJUL 77 49.0 12JtJN77 12.0 31'4AY77 12JUN77 1i!.O 7JIIN77 7.0 31MAY77 7JuN77 7.0 1JtJN77 0.0 15JUL77 15JUL77 o.o I ~JIIN77 14.0 12JUL77 2bJUL 77 111.0 27JUN77 2&.0 10JUN77 ?bJUL 77 i!&.o ?OJ IlL 77 119.0 14JUN77 2AUG77 4CJ.o 1~JUN77 12.0 1f>JUtH7 28JUN77 li!.O 8JIIN77 7.0 21JUJI477 211JUN77 7.0 21\JJlN77 12.0 1fiJUN77 28JUN77 1i!.O 30JJJN77 13.0 i!JUL77 15JUL77 u.o q.JIJL 77 18.0 2\JUN77 IIJUL77 u.o 28JUIH7 7.0 21JUN77 28JUN77 7.0 \ q.JllL 7 7 28.0 21JUN77 19JUL 77 i!B.o ~ 1JilL 77 39.0 211Jl1N17 2AUG77 J'J.O l OJIJL 77 18. 0 15JUL77 2AUG77 18.0 29Jtl"'77 7.0 2f>JUL77 2AUG77 7.0 20JtJL77 i!B.O 5JUL77 i!AUG77 i!B.O 24JJJL77 179.0 4FER77 i!AUG17 179.0 lbJIJL77 0.0 i!AUG77 i!AUG77 0.0 ]AtJG77 0.0 9AUG77 9AUG77 o.o w ....... t,l:j '"d t110EC7b 124.0 29SEP7& 31JAN77 ll4.0 E'" J:- 00 1-' 2MAR77 205.0 9AUG7b i!14AR77 i!05.0 00 Vl I (j\ .,.... I ~ FIGURE 29 CONT. SEflii[NCf 1-J PAGE II TfiT S T A R T STAAT F I N I S H FIN w t>:1 (l) ( J) 0 E S C k I f' T I fl 11 OUIUT CAL EARLY LATE FLOAT EARLY LATE FLOAT ...... "' :.t> bO'l &10 f>l C? 1><'0 w llHIV[W ~ loiSTALL STORM OkA!tur.E o.o bO.O 71 71 'IAUG7b C?1AIIG7& 31JAN77 JMAR77 175.0 1'14.0 'IAUG7b I'IOCT7b 31JAN77 114AY77 175.0 1'14.0 c (JQ ex; 0\ .p.. ...... L11 I ...... I &12 1>15 IIIJTSTUE PLII~-1~ (N(j 45.0 71 30SEP7b IAMAR77 lb'l.O 11N0y7b 1MAY77 16'1.0 .p.. btL' 1>1~ nuTS!Uf ELECTRICAL '10.0 71 .50SEP7b 1FEH77 124.0 280EC7b 1MAY77 124.0 &IS b?O W o.o 71 11NOV7& I"'AY77 11>9.0 !3NOV7b tNAY77 169 0 0 b1'; &So k o.o 71 13NOV7b 2&JUL77 255.0 13NOV7b 26JUL77 255.0 &1'1 bC?O R o.o 71 280EC7b \MAY77 124.0 280EC7b 1MAY77 124.0 b1'1 b'lll H o.o 71 28DEC7b 2&JUL77 210.0 28DEC7& 2bJIIl 77 210.0 &20 b?~ SuRr.RAflt ~ HASE FUR PAVINb 42.0 71 29DEC7& 2MAY77 124.0 8FEH77 12JUN77 124.0 &25 &30 CtrRii 1. f.IJTTEH 21.0 71 9FER77 13JIJN77 1<'11.0 IMAA77 3JUL 77 124.0 b30 b~'l ~Al.KS 21.0 71 ?"'AR77 IIJIJL 77 124.0 Z2MAA77 24JUL77 124.0 &Jtl b4~ ASPHALT PAV(~(j 10.0 71 ?MAR77 15JUL77 115.0 ltMAR77 24JUL 77 135.0 0\ I bJ'j &4'> R o.o 71 22MAR77 ?.IIJtJL77 1211.0 22MAR77 ?4JUL 77 124.0 ...... N &4'i 1>5') TIIPSOIL " Fl"Jf. GRAOING 1&.!1 71 2~MAH77 25JUL77 1211.0 7APA77 'lAUGH 124.0 b'JO f>S'l TEST MfCH " ELECT 14.0 71 11JIIL77 27JIJL77 14.0 2&JUL77 9AUr.77 14.0 &55 bbO SlLL JOtl c;.o 11 l0AilG77 10AIJG77 0.0 IIIAIIG77 t IIAUG 77 o.o PROJFCT RASt UATf I Jtll 71> PRIIJHT OIIRATION 1110.0 PROJECT COMPLETION DATE 14 AUG 77 FIGURE 29 CONT. - - IRM PROJECT CONTROL SYSTEM JUL 76 RUII OATE JUL 7b • * S C H E 0 U L E R E P 0 R .T • • DATA DATE RUII SE IJUE IIICE 0 Nt. TNOWK I 0 I I I OA DISPENSARY-LACKLA~O AFB TX ~ONTEOON CONSR FROM JilL 76 TO 14 AUG 77 -~~~~~~:~--~-~-------------------------------------------;~;--------~-;-;-;-;------·;;;;;----;-i:~~i-;-~-~-----;i;- 0 N DURAl CAL EARLY LATE FLUAT EARLY LATE FLOAT (1) (J) D t. S C R I P T I 5 NTP 1.0 71 1JUL7b I JIll 7ft 0. 0 1JUL16 1JUL76 o.o 5 I 0 M(J8 ~ LAYIIIIT 7.0 71 i'JIIL7b i'1 Jlll7, 25.0 8JUL7t. 2AUG76 25.0 5 i'O SUB 1\ APP Mt:r:H 1\ ELfC T WOUf.H-1111 MTL S 30.0 71 2JIJL7b JJUL7b 1.0 31JUL76 UUG76 1.0 5 25 SUR SH 0>\IGS PAIII FORtiS 20.0 71 i'JUL7h 17AIIG7fl 11&.0 21JUL7& 5SEP76 46.0 5 30 SIIR Sli OWGS METAL OOOR HIICKS 20.0 71 2JIIL7b ?2AUG76 51.0 21JUL7t. 10SEP76 51.0 5 35 SIIR SH D>IIC:.S STRUCT STL & JlliSTS 30.0 71 2JUL 7b l2Allt.7b 111.0 HJUL76 10SEP76 41.0 115.0 5 40 StiR 1\ APPWOV ~IASOIIRY rUTLS 115.0 71 <'JliL 7h ;:>~OCT7b 115.0 15AUG7& 8DEC76 5 115 SUH Sli OWbS MTL WIIIIOOwS 30.0 71 2JliL7b IOSEP7b 70.0 31JliL7& qocn~ 7o.o 5 50 SUR I.IST 1\ S~'IPLFS t!LO~S flAIWIIARE 30.0 71 ?JIIL7h 1i?Sf.P7b 72.0 :SlJUL7& ll0CT76 72.0 ~ q7.0 15AUG7b 20NOV76 q1.0 I 5 5~ SUR SH O~GS ALUM t.NTR 1\ MTL DOORS 115.0 71 i?Jf.IL7h 70CT7b...... l.V .., bO Sill~ L1\ Ttt II PLASTER 4'5.0 71 i?JIJL7b i?50EC7b 17&.0 t5AUG76 7FE877 176.0 11'5.0 71 ?JliL7b ll0fC7b 1&4.0 15AUG7& 2t.JAN77 164.0 ') ~5 SUH CERAMIC TILE 5 70 SIIRMIT TOlLt.T PARTITIONS & ACCFSSURIES 115.0 71 ?JliL7b 12fE877 2?5.0 t5AUG76 28MAR77 225.0 5 75 SUR~IT PLUMB 1\ MECH FtXT 1\ EQUIP :so.o 71 2JIIL7h i?OOCT76 110.0 31JUL76 18"10V76 110.0 5 80 SURf1J T ELECT f I XT & fOIJIP 30.0 71 i'JIIL7b 170Er7b 1&8.0 J1JUL76 15JAN77 1&8.0 5 A') SIIB 1\ APP SH UNGS MISe ~1fTALS 11'5.0 71 ?JIIL7b 170CT7b 107.0 15AUG7b 30NOV7b 107.0 5 QO SUR 1\ App SH 0>\IGS REINf STL :sc;.o 11 ?JIIL7b 2JuL7b 0.0 5AUG7ft 5AtJG76 o.o 5 Q~ SURMIT & APPWOV ROOF nECK Stt UWGS 11'5.0 71 2'JIIL7b 2h0CT7b ll&.o 15AUG76 90fC7& 116.0 5 I 00 SUB~I! T WOUF 1\ SliFE T!lf TAL S~OP Oii!';!> :so.o 71 <'JIJL7h ROCT7h qs.o 31JUL7& 6NOV76 q8.0 l.Vt:%j .., I 0 5 Slf8 M IT X-1< A Y P R.fl Tfl: TT nN :so.o 71 ?JliL7b t>SOCT7& 113.0 31JUL76 21NOV76 113.0 1-'t;:l ., 11. APPROV fllllll< cA:·JOPJES & S11;t~<; 115.0 71 2JIJL7b ?hMA~77 2&7.0 t5AUG76 91'1AY77 2&7 0 0 >.: .p.. !10 Sllfii~IT CIQI-' 1.11 001~ .......I .p.. FIGURE 30 SEQUENCE E S ~ PAGE 2 ------------------------------------------------------------------------·--------------------------------------------- (I) (J) 0 E S C H I P T I 0 N TOT DUAAT CAL S T EARL 'I A A T LATE STAAT FLOAT F I EAAL'I N I S H LATE FIN FLOAT Wt:>:~ 1-''"d ----------------------------------------------------------------------------------------------------------------------c; 115 SUBMIT PAINT SAMPLES 30.0 71 lJllL76 19JAN77 201.0 31JUL7b 17FE877 201.0 > I;:~QQ ...... V1 001 5 ti»U SURMJT VINYL wALL COVERING 30.0 11 2JUL7b 22~AH77 2&3.0 31JUL7b l0APA77 263 o 0 0\i-' J ~ '5 12'5 SURMIT S~ O~r,s MILtWOAK 30.0 1t 2JUL 7_& 2SOEC7b 17&.0 31JUL76 23JUI77 1h.O 5 t 30 SIIB~IIT ~ESILIENT FLOOR SAMPLES 30.0 1t 2JIJL7b 23FF.R77 236.0 31JUL7b 24"'AA77 236 o 0 '5 135 SURMIT SH O~GS CASEwORK 4'5.0 71 2JUL7b 27NQV7b 148 0 0 t'5AUG76 10JAN77 148.0 '5 140 SURMJT HOSPITAL A MISC lQIJIP 4'5.0 71 2JIIL7b 170CT7b 107.0 15AUG7b 30NOV76 107 0 0 '5 145 SUBMIT MISC HLOG EQUIP 30.0 71 .?JIIL7b i!MAR77 243 0 0 31JUL7b 31"'AA77 243.0 5 1'50 CONC DES MIX 1'5.0 71 2JUL7b 6AUG7b 35.0 1bJUL76 .i»OAUG76 35.0 5 330 PRE-QUALIFY ~ELDERS :u.o 71 2JUL7b 30NUV7b 151.0 11JUL76 .i»90EC76 151.0 5 600 SUB I APP SH DWGS OUTSIUE ELEC & PLU~H 4'5.0 71 lJUL7b 3NOV7b 124.0 t5AUG76 17DEC76 124.0 10 1'5 ROUGH GRAO & EXCAV BLDG t4.0 71 9JIIL7b 3AUG76 25.0 22JUL7b IUUG76 25.0 111 60~ DEMOL A SITE GRADING 32.0 71 9JUL7b 31DEC76 175 0 0 9AUG76 31JAN77 175.0 2'5 1&0 GOV'T APPHOV PAN fORMS 1'5.0 71 22JUL 7b bSEP76 46 0 0 5AUG76 .i»OSEP76 11&.0 30 lh'5 GOV'T APPHOV ~TL OR RUCKS ts.o 7t 22JIJL7b 11SEP7b 51.0 5AUG76 25SEP76 51.0 "' I ...... . 1'5 1'55 A n.o 11 22JIIL7b 1&AUG 7ft 25.0 2lJUL7b tUUG7b 25.0 ~ 15 2b'5 N o.o 71 2i'JUL7b 20AUG7b 29.0 2i»JUL7& 20AUG7& 29.0 20 !55 DEL MECH & ELECT ROIJGH•IN MTLS INITIAL 15.0 71 1AliG7b 2AIJG76 1.0 1'5AUG7b lbAUG7b 1.0 35 170 GOV'T APPROV STH STL AJSTS 20.0 71 JAUG7b t1SEP76 41.0 20AUG76 30SEP7b 41.0 4'5 180 GOV'T APPHOV MTL ~INDOWS 20.0 71 UliG7b 100CT7b 70.0 20AUG7b 2qocn& 10.0 50 18'5 GOV'T APPROV BLORS HARD~ARf 30.0 71 IAUG71> 120CT7b 72.0 30AUG7b IONOV7fJ 1l.O 75 210 GOV'T APPAOV PLUMB & MECH FIXT & EQUIP 30.0 71 1AUG7b t9NOV7b 110.0 JOAUG7& 18DEC7b 110.0 80 21'5 GOV'T APPt-~OV ELECT FIMT A ElllliP 30.0 71 IAUG7b 1bJAN77 1&8.0 30AUG7& IIIFEB77 tfJ8.0 100 220 GUV'T 4PP~OV ROOF A SHMTL SH O~GS t':i.O 71 1AIIG71> 7NOV7b 98.0 15AUG76 <'1NOV76 98.0 EARLY START SORT ABBREVIATED HERE FIGUP£ 30 CONT. 18~ PROJECT CONTROL SYSTE~ Rur~ fiATE JIJL 7b * * SCHEOULE R E P 0 R T * * DATA DATE JUL 7& RUIJ ')[OIItNCE 0 NETWORK 10 ltl OA 01SPENSARY-LACKLA~O AfR TX ~O~TEDON CONSR FROM JIJL 7b TO 14 AUG 77 -~~~~~~:~__ :_~------~------------------------------------;~;-----------;-;-;-;-~----;;;;;----;-;~~:;-;-~-~-----;;~- (1) (J) 0 E S C R I P T I 0 N DURAl CAL EARLY LATE FLOAT EARLY LATE fLOAT ----------------------·------------------------------------------------------------------------------------------------ I. 0 71 1JIIL7b 1JIIL 7& 0.0 1JIIL7b 1JUL7& o.o 5 NTP 5 QO SUB ~ APP SH DWGS REINf STL 3'5.0 71 2JIIL7b 2JIIL76 0,0 5AUG76 5AUG7b o.o -... 5 20 SUB & APP MtCit & ELECT ROUGH-IN MTLS 30.0 71 2JUL7b 3JIJL76 1,0 31JUL76 1AUG7& 1.0 5 10 MOR & LAYOUT 7.0 71 2JUL7b ?7 JUL 7& 25,0 8JUL76 2AUG7& 25.0 20 155 DEL MECH ~ ELECT ROUGH-IN MTLS INITIAL 15.0 71 1AIIG76 2AIJG7b 1,0 15AUG7b 1bAUG7b 1.0 9JIIL7& '5AIJG76 25,0 22JUL7& t&AUG7& 25,0 10 15 ROUGH GRAD & EXCAV t:ILDG 14.0 71 1'5.0 71 2JUL7b bAUG76 15,0 16JUL76 20AUG76 3'5,0 5 150 CONC DES MIX UliG76 &AtJG76 0.0 20AUG76 20AUG7& o.o QO 150 DEL REINF STL 15.0 71 12AIJG7b 111.0 31JUL76 10SEP7& 111,0 5 ~5 SUR SH OWGS STRUCT STL ~ JOISTS 30.0 7l 2JUL76 o.o 71 22JUL7& 16AtJG76 25,0 22JUL76 1bAUG7& 25,0 15 155 R0'1 20.0 71 2JUL76 17AIJG7& 11&,0 21JUL7& 5SEP76 11&,0 .......I 5 25 SUR SH OWGS PAN FORMSV1 10.0 71 1&AIIG7b 17AUG76 1.0 25AUG76 2f>AUG76 1.0 155 275 ROIIGH-IN UNDER ASIH 15 265 R o.o 71 22JIIL76 20AUG76 29,0 22JUL76 20AUG7& 29,0 o.o 71 20AUG7b 20AUG7b 0.0 20AUG76 20ALJG7b o.o 150 265 R t&,O 71 2UUG7b 21AIJG76 0,0 5SEP7& 59EP7& o.o 265 270 flGS & PLINTHS 5 30 SUR SH OWC.S METAL DOOR SliCKS 20.0 71 2JUL7b 22AliG7b '51 • 0 21 J UL 7 6 109EP7& 51,0 20AUG76 26AUG76 b,O 20AliG7& 2&AUG76 &.o 150 275 R o.o 71 111.0 71 2&AUG7b 27AUG76 1.0 8SEP7'· 99EP76 1.0 275 2AO RASMT FNO, SLAB, BMS 25 lbO GOV'T APPROV PAN FORMS 15,0 71 22JUL76 &SEP76 116,0 5AliG7& 209EP76 46,0 wtx:J r-o'"d 270 300 GRAUE RfAMS 30,0 7t 6SEP7b bSEP7b o.o 50CT7b 50CT7& o.o E'"+' 30,0 71 2JUL76 10SEP7& 70,0 31JUL76 90CT76 70,0 OQ ..... ') 45 SUR SH OWGS MTL WINOOWS V1 col 0'11-' +'I FIGURE 31 SEQUENCE L S ~ PAGE 2 TOT S T A H T START F I N I S H FIN(Il (J) 0 E S C R I P T I 0 N DURAl CAL EARLY LATE FLOAT EARLY LATE FLOAT w 1:':1 ....... ~ 280 2R5 BASMT WALLS !)> 21.0 71 'ISEP7b 10SEP7b 1.0 2'1SEP71> 30SEP7b 1 • 0 ~ ~ ()Q ....... 30 11>0:. GOV'T APPWOV MTL OR BuCKS V1 15.0 71 22JUL71> 11SEP7b 51.0 5AUG7& 2'5SEP7b '51.0 col 0\1-' 35 170 GOV'T APPHOV STR STL ~JSTS 20.0 71 1AIIG71> IISEP7b 111.0 20AUG7& JOSEP7b 41.0 ~ I 5 50 SUB LIST A SAMPLES ~LORS HARO~AkE 30.0 71 2JUL71> 12SEP7b 12.0 31JUL7b 110CT1b 12.0 11>0 315 DELIVER PAN FORMS 115.0 71 bAUG71> 2tSEP7b 11&.0 I'ISEP7b 4NOV7b llb.O lb5 325 FAR ~ DtLIVEH MTL DH BUC~S ~o.o 11 I>AUG7b 2&SEP7b 51.0 3NOV7& t'IIOEC7b '51. 0 170 330 FAR & DEL STR STL & JSTS '10.0 71 21AIIG7b 10CT7& 111.0 18NOV71> 2'10EC7b 41.0 285 300 OAMPPHOOFING 5.0 71 50SEP7b 10CT71> 1.0 40CT1& 50CT7& 1.0 300 JIO F&B ~ GHAUE urWER BLDG 10.0 71 bOCT1b b0CT71> 0.0 150CT7b 150CT7b o.o 5 55 SUR SH UWGS ALUM ENTH & MTL ODORS 115.0 71 2JliL71> 70CT71> '17.0 15AUG7b 20NOV7b '17.0 5 100 SUBMIT HOOF & SHEETMETAL SHOP DWGS 30.0 71 2JUL7b 80CT7f> '18.0 31JUL1b bNOV7b '18.0 115 1~0 GOV'T APPHOV ~TL WINDOWS 20.0 71 UUG71> IOOCT71> 10.0 20AUG7b 2'10CT7b 70.0 50 !85 GOV'T APPHOV BLuRS HARD~•RE 30.0 71 tAliG71> 120CT7b 72.0 30AliG7& IONOV7b 72.0 310 315 30l IINPR FLR MECH & ELECT R-1 20.0 71 I bOCT11> 11>0CT7f> 0.0 IINOV7& 4NOV7b o.o 0\ I 5 R5 SUB & APP ....... SH D~GS MISC METALS 115.0 71 2JUL7b 170CT7b 107.0 !'5AUG7& 30NOV7b 107.00\ 5 14~ SUBMIT HOSPITAL & MISC EQUIP 115.0 71 2JUL7b 170CT7b 107.0 1'5AUG7& 30NOV7b 107.0 5 75 SUBMIT PLUMB & MECH FIXT & EDUIP JO.O 71 2JliL71> 200CT7b 110.0 31JUL7b l8NOV7b 110.0 5 !05 SUBMIT x-RAY PROTECTION 30.0 71 2JUL7b 230CT7& 113.0 31JUL7& 21NOV7& 113.0 5 110 SuB ~ APPROV MASONRY MATLS 115.0 71 2JtJL7b 250CT7& 115.0 15AUG7& 8DEC7b 115.0 5 q5 SUBMIT & APPROV ROOF DECK SH OWGS 115.0 71 2JIJL7& 2bDCT1b 1111.0 15AUG7b 'IOEC7b 1lb.O 180 51>0 FAR & DELIVER METAL WINDOWS '10.0 71 2UUG7b J00CT7b 70.0 18NOV7b i>7JAN77 70.0 5 bOO SUR ~ APP Stf Qi~jGS OUTSIDE ELEC & PLUMB 45.0 71 2JIIL7b 3NOV76 1211.0 1'5AUG7& 170EC7b 124.0 315 320 FPC PAN SLA~S ~ BMS 50.0 71 '5NOV7b 5NOV7& 0.0 240EC7b 240EC7b 0.0 LATE START SORTABBREVIATED HERE FIGURE 31 CONT. ~~~ PROJECT CONTROL SYSTEM DATA DATE JUL 7& RUII OA TE JUL 7& • • S C H E 0 U L E R £ P 0 A T • • RUIJ SE!HIENCE 0 NUI'lORK IO Itt OA OISPENSANY•LACKLANO AFB TX MONTEDON CONSR FROfil JUL 7& TO l4 AUG 77 -~~~~~~=~--~-~~------------------------------------------;~;------~----;-;-~-~-;-------;;~;;----;-i~~~i-;-~-~-----~ (1) (J) 0 E S C R I P T I 0 IJ OIJRAT CAL EARLY LATE FLOAT EARLY LATE FLOAT 5 NTP t.o 11 1JUL 7& 1JUL7& 0.0 IJUL7& IJUL7& o.o 5 90 SUR ~ APP SH OWGS REINF STL 35.0 71 2JUL7f> ?.JUL 7& 0.0 5AUG7& 5AUG7& o.o 90 150 OEL RETNF STL 15.0 71 UUG7& f>AIJG7& o.o 20AUG7b 20AUG7& o.o 150 2&5 R o.o 71 20AUG7& 20AUG7& 0.0 20AUG7& 20AUG7& o.o 2&5 270 Flf.S & PLINTHS 1&.0 71 2UUG7& 21AIIG7& 0.0 5SEP7& 5SEP7& o.o 270 300 GN40E REAMS 30.0 71 &SEP7& &SEP7& 0.0 50CT7b 50CT7& o.o 10.0 71 &OCT7& &OCT7& 0.0 150CT7& 150CT7& o.o 300 :u 0 F1!.11 ~ G~AL•E m1UE R RLDG 310 315 30l IIIJPf.l HR t~ECH & ELECT R•l 20.0 71 1&0CT7& 1&0CT7f> o.o 4NOV7b 4NOV7& o.o 5NOV7& 5NOV7b o.o 24DEC7& 24DEC7& o.o 315 320 FPC PAN SLAHS ~ BHS 50.0 71 70l UNOR FLR MECH & fLECT R-1 50.0 71 5NOV7& 5NOV7& o.o 24DEC7& 24DEC7& o.o 0\ 315 325 ......I o.o 71 24DEC7& 240EC7& o.o 24DEC7& 240EC7& o.o -...J 320 325 R r~fTAL RUCKS 5.0 71 250EC7& ?50EC7& 0.0 29DEC7& 29DEC7& o.o 325 330 EI~ECT STL COLS & •. 8JAN71 o.o BO 350 ERECT SlR STL 1!. J0TSTS 10.0 71 300EC7& 100EC7& 0 .o 8JAN77 12.0 71 9JAN77 9JAN77 0.0 20JAN77 20JAN77 o.o 350 355 ROOF DECK 355 3h~ ROOFING & SHT MTL 2t.o 71 21JAN71 21JAN77 0.0 10FEB77 tOF£877 o.o 3&5 ~q5 AC lliiCT,IORK 5&.0 71 11FEB77 11FEB77 0.0 7APR77 7APR77 o.o 14.0 71 8APR77 IUPR77 0.0 21APR77 2UPR77 o.o 3q•; 4t U CE. TLr. StJSP SYST & IIJSIIL 12.0 71 22APR77 22APR77 0.0 3MAY77 3MAY71 o.o 4110 '1~0 PLAS CLG 4130 441'j 10l PA lilT & F I II ISH 28.0 71 IIMAY77 41MAY77 0.0 31MAY77 31MAY77 o.o o.o 115.0 71 1JUN77 1JIIN77 0.0 15JUL77 15JUL77 WJ:%l 4415 505 'lO'l rUMP PAINT 1!. FIN 1-''"d sue; ~10 ~Ol PAINT & FINISH 18.0 71 1&JUL77 1 &JUL77 0.0 2AUG77 2AUG77 o.o ~c ..,_ ()QI--' -l.n 001 0\ ...... I ..,_ FIGURE 32 SEQUENCE F FL PAGE l (l) (J) TOT S T A R T START F I N I S H FIN WI:>:! 0 E S C A I P T I 0 ~ DUIUT CAL EARLY LATE FLOAT EARLY LATE FLOAT ~-'."d -----------------------------------------------------------------------------------------------------'~,~---------------->r:: ~ 510 b55 CLEAN•UP BLDG ()Q ...... 7 .o 71 JAUG77 3AUG77 0.0 4UUG77 ·.,9AUG77 o.o VI001b55 bbO SELL JOB. 5.0 71 10AUG77 10AlJG77 0.0 1UUG77 1hUG77 "'~-' o.o I 5 20 SUB A APP MECH & ELECT ROUGH•IN MTLS \ 30.0 71 2JUL7b ]JUL 7b 1.0 31JUL76 UUG7b 1.0 ~ 20 155 DEL MECH & lLECT kOUGH•IN MTLS INITIAL 15.0 71 UUG7b 2AUG7b 1.0 15AUG7b 1UUG7b 1.015'; 275 ROUGH•IN UNDER SSMT 10.0 71 1bAUG7b 17AIJG7b 1.0 25AUG7b 26AUG76 1.0275 280 8ASMT FND, SLAR, SMS 14.0 71 2UUG7b 27AIJG7b loU 8SfP7b 9SEP7b 1.0280 285 RASMT WALLS 21.0 71 9SEP7b 10SEP7b loO 29SEP76 30SEP76 1.0285 300 nAMPPROOFING 5.0 71 30SEP7b IOCT7b 1.0 IIOCT7b 50CT7b 1.0410 445 ACOUIST & OTHER CEILINGS 35.0 71 22APR77 27APH77 5.0 26MAY77 31MAY77 5.0150 275 A o.o 71 20AUG7b 26AUG7b. boO 20AUG76 26AUG76 6.01145 470 R o.o 71 31MAY77 7JUN77 7.0 31MAY17 7JUN77 7.01170 480 RESIL FLR 21.0 71 1JitN77 8JUN77 7.0 21JIIfH7 28JUN77 7.0480 490 II o.o 71 21JUN77 28JUN77 7.0 ·21JUN77 28JUN77 7.0490 510 li~ST HOSP "'I II. MISC fl'llliP 35.0 71 22JIJN77 29JIJN77 7.0 26JUL77 2AUG77 7.0 ...... 00 II liS 4b5 A o.o 71 31MAY77 12JUN77 12.0 ]IMAY77 12JUN77 12.0llb5 1175 JljSf 5011; ~11LLWflRK 1f>.O 71 1JIJN77 . 1]JIJN77 12.0 lf>JUN77 28JUN77 12.01175 1180 R o.o 71 1bJUN77 211JtJN77 12.0 1bJIIN77 28JUN77 12.01175 505 COMP MILLWORK 11>.0 71 17JUN77 30JIIN77 13.0 2JUL 77 15JUL77 13.03b5 370 R o.o 71 10FEB77 24FEB77 111.0 10FE877 24FER77 14 .o370 390 I~TERIOk PARTITION 42.0 71 11Ff1177 25FE877 14.0 2111-1AA77 7APR77 14.0390 395 H o.o 11 24MAR77 7APR77 111.0 24MAR77 7APR77 14.01130 4110 R o.o 11 3MA'I'77 17MAY77 111.0 3MAY77 1714AY77 Ill. 04110 b50 I~ST r1FCH ELIIIIP 1o.o 11 4MAY77 18MAY77 14.0 12JUL77 26JUL77 111.0 TOTAL FLOAT SORTABBREVIATED HERE FIGURE 32 CONT. IRM PROJECT CONTROL SYSTEM RUil flATF I JUL 7t, * * LU"'P SIJM COST REPORT * * DATA DATE 1 JUL 7et 14 AUG 77 RU~. St:.Oili::'IICE 0 NETt~OWK 10 ttl TITLE OA OISPE~SARY-LACKLAND AFB TX MONTEOUN CONSA FROM JUL 7b TO PAGE SEQUENCE E S OHGANilATION ACTUAL START REMAI PERCNT FINISH I ESTIM 0~ I DATE OUR AT COMPL T DATE FLOAT I COST COST T•D WI 0 E S C R I P T I 0 N tJUL7b 1.0 .o tJUL7b .o 1 o. o. 1 5 NTP 2JUL 7b 7.0 .o 2AUG7b 25.0 I 2000. o. 5 10 MOB & LAYOUT o. o. s 20 SIIB 1!. APP MECH ~ ELECT ROUGH-IN MTLS 2JUL7b 3o.o .o UUG7b t.o I o. o. 5 2'i SUO SH DWGS PAN FORMS 2JUL7b 20.0 .o 5SEP7b 4b.O I o. o. 2JUL7b 20.0 .o 10SEP7b st.o I 5 30 SIIB SH OwGS METAL OOQR RUCKS I o. o. 2JUL7b 3o.o .o 10SEP7b II l.0 5 35 SUB SH Ot4GS STRIICT STL & JOISTS 115.0 I o. o.5 110 Sll8 & API'WOV MASONRY MAlLS 2JUL7b 45.0 .o 8DEC7b 70.0 I o. o.5 45 SUB SH OwGS MTL ~INDQWS 2JUL7b 3o.o .o 90CT7b 72.0 I o• o. 30.0 • o 110CT7b SAMPLES RLDRS HARDWARE 2JUL7b 5 ')0 SUO LIST ~ 45.0 .o 20NOV7b 97.0 I o. o. o\ MTL DOORS 2JUL 7b 5 ~5 Sll8 SH OI'IGS ALUM ENTR 2JUL 7b 115.0 .o 7FES77 17&.0 I o. o. bO SIIB LATH & PLASTER o. 5 2JUL7b 45.0 .o 2bJAN77 1&4.0 I o. 5 b5 SUB CEIU~IIC TILE 28MAR77 225.0 I o. o. SUBMIT TOILET PARTITIONS & ACCESSORIES 2JUL7b 45.0 .o 5 70 2JUL7b 3o.o .o 111NOV7b llO.O I o. o. 5 75 SU~MIT PLU~~ & MECH FIXT & FQUIP 15JAN77 1&8.0 I o• o. FIXT & EOUIP 2JUL7b 30.0 • o 5 80 SUBMIT ELECT 30NOV7b 107.0 I o. o. & APP SH OWt;S MISC METALS 2JUL7b 45.0 .o 5 d" SIIR ~ APP SH DwGS REINF STL 2JUL7b 35.0 .o 5AUG7b .o I o. o. 5 90 SUB 9DEC7b 11&.0 I o. o. 5 95 SUBMIT & APPIIOV ROOF DECK SH DWGS 2JUL7b 45.0 .o bNOV7b 98.0 I o. o. ~ SHEETMETAL SHOP OWGS 2JUL7b 30.0 .o 5 too SURMIT ROOF .o 21NOV7b 1\3.0 I o. o. 5 toe; SU~MIT X-RAY PROTECTION 2JUL7b 3o.o 9MAY77 2&7.0 t o• o.~ APPWOV DOOR CANOPIES & SIGNS 2JUL7b 115.0 • o 5 1"1 0 SUBMIT .o 17FEB77 201.0 I o. o.s 115 SUBMIT PAI~T SAMPLES 2JUL7b .30. 0 .o 20APR77 2&3.0 I o. o.5 120 SUSMIT VINYL WALL COVERING 2JUL7b 3o.o .o 2]JAN77 17b.O I o. o. I SIIBMIT SH DO'IGS MILLWORK 2JUL7b 3o.o 1.0 s 1]0 45.0 .o 10JAN77 148.0 I o. "'I-" s 125 SIIBMI T RESILIENT FLOOR SAMPLES 2JUL7b 3o.o .o 24MAR77 23&.0 I o. o.o. SU~MIT SH U~GS CASEWOPK 2JUL7b o. 115 45.0 • o 30NOV7b 107.0 I o• 5.., 111(1 SUBMIT HOSPITAL & MISC EQUIP 2JIJL7b o. 2JUL7b 30•.0 .o ]tMAR77 2113.0 I o. 5 145 SUbMIT ~ISC BLUG EQUJP 15.0 .o 20AUG7& 3"5.0 I o. o.c; ,..,0 CONC OES MIX 2JUL7b o. 2JIJL7b 3o.o .o 29DEC7b 1'51.0 I o. 5 BO PRE·OIIAL IFY wELDEPS 45.0 .o 170EC7b 124.0 I o. o.5 bOO SUS & APP SH DwGS OUTSIDE ELEC & PLUMB 2JUL7b 111.0 .o 1bAUG7b 25.0 I 4000. o. 9JUL7b 10 1') ROUI;H GRAD & EXCAV SLOG 9JUL7b 32.0 .o 31JAN77 175.0 I 10000. o. 10 bUS OEMOL & SITE GRADING 22JUL 7b 15.0 .o 20SEP7b 4b 0 0 I o. o.25 loO GOV'T APPROV PAN FOPMS 22JUL7b 15.0 .o 25SEP7b 5t.o I o. o.30 lb., GOV'T APPROV MTL OR 811CKS o. lc; 1S<; R 22JUL7b .o .o 1bAUG7b 25.0 I o. o.2f>'i A 22JUL7b .o .o 20AUG7b 29.0 I o. o. 1'5 UUG7b 15.o .o 1bAtJG7b t.o I 13000. 20 ISS UEL MECH ~ FLECT ROIIGH-lN MTLS INITIAL o. o. UUG7b 20.0 .o 30SEP7b 111.0 I35 1 7 0 GOV'T AP~ROV STR STL ~JSTS 1AUG7b 20.0 .o 290CT7b 10.0 I o. o. 45 180 GOV'T APPAUV MTL WINOOftS Wl:'=j1-"'"d ~-1:- ()Q f-< IJ1CXll 0\i- ~ 7h • • LU'"IP SliM COST REPORT o * DATA DATE 1 JUL 7b ()Q 1--' 1.1"1 RUN SErJIIE.NCf CX>I 0 tH. Tr~llRI< IIJ Ill TITLE DA Ol~Pf~SAWY•LACKLANO Af8 TX MONTEOON CONSR HOM JUL 7b TO 14 AUG 77 0'>1--' SEIWfNCf E S ORGANIZATION ~I PAGE 2 •II 0 f S C R~ I l P T l START REI'IAI PFRCNT fiNISH I ESTIM 0 ACTUAL0 N DATE DURAl COMPLT DATE FLOAT I COST COST T•O -----------------------------------------------------------------------------------------------------------------------· 50 IRe; GOV' T APPWIJV HLOI]"i GOV 1 T APPHIJV COLrlR SEL VINYL WALL COVERING IAUG7b 30.0 .o 20HAY77 2b3.0 I o. o. 125 (>40 GfiV 1 T APPWOV MILLWORK 1AUG7& 20.0 .o 12FEB77 176.0 I o. I JO 211" GOV 1 T APPRllV A COLOR SEL kESILIF.NT FLOOR o • 1115 2b0 c,OV 1 T APPROV .,.ISC IILOG EQIIIP IAUG7& 30.0 .o 23APR77 236.0 I o. o. 90 J'jO OEL Rf l ~F :HL IAUG7& 20.0 .o 20APR77 243.0 I o. o.lbO 315 O~LTVEk ~A~ FORMS bAUG7b 15.0 .o 20AUG7b •o I 11000. o. bAUG7b 45.0 .o 4NOV76 46.0 I lh'l 3(!5 FAR & UfLIVfH MTL o. o. bOS b10 H OR RUCKS bAUG7& 90.0 .o 2110EC76 51.0 I 2000. o.biiS bl2 R qAUG7& .o .o 2MAR77 205.0 I o. o.110 175 DfLIVEk MASONRY MAllS qAUG7b .o .o 31JA~77 175.0 I o. o.lbAUG7b 45.0 2t>JMH7 55 JQO GOV'T APPROV .o 115.0 I 9500. o. ALIIM ENTR & MTL DOORS 1bAUG7b 20.0 .o 10DEC7& 97.0 I o.0'> bO 195 &OV 1 T APPROV LATH & PLASTER lbAUG7b 15.0 o. I .o UFE877 176.0 I o. o.N b5 200 GOV 1 T AP~ROV CER TILE & COLOR SEL lbAUG7b 30.0 .o 2SFE877 lb4.0 I o. o.0 70 205 GOV 1 T APPROV TOIL PART & ACCES 1bAUG7& 20.0 .o I HPR77 225.0 I o. o. 8S ~05 FA6 ~ ~ELIVER MISC METALS lbAUG7b 45.0 .o 14JAN77 107.0 I 3500. o.95 'So OELTVFR HOOF DECK MATLS lbAUG7& 30.0 .o 8JAN77 11b.O I o.110 500 DELIVER uOOH CANllPIES & SIGNS 1bAUG7b 75.0 .o 23JUL77 2&7.0 I 2000. o.13S 250 GOV 1 T APPtlOV .CASEWORK 1bAUG7& 30·~o .o 9FE877 148.0 I o.140 t>SS GOV 1 T APPHUV HOSP & MISC EQUIP 1&AUG7& 30.0 .o 30DEC7b 107.0 I o. o. IS':i 27"i HOuGtt•lN UNDER BS'"IT I&AUG7b 10.0 .o 2bAUG7b 1.0 I o. o. ·2?0 JSS ~FAB-&" OEL I~~-SHJ-ITL 2000. o • & ROOF I &AUG 7_& t.o.o .o 20JAN77 98.0 IbOO hl2 OEL MATLS OS ELEC & PLUMB lbAUG7b 45.0 31 JAN77 o. o • 150 •o 124.0 I o. o • 2b5 H 20AUG7b • o .o 20AUG76 •o I o• o. ISO 27'S H 20AIIG76 • o .o 2f>AUG7b 6.0 I o. o. 150 biO H 20AUG7b .o .o 2MAH77 194.0 I o. o. 170 325 FAH & UEL STL COLS 2tAUG7b 45.0 .o 24DEC7b 81.0 I 1500. o.170 330 ~AH & DEL STR STL & JSTS 2JAUG7b 90.0 .o zqoEC7t. 41.0 I 111000. o. 180 ~bO FAH & DELIVER METAL wi~OOWS 21AUG7b 90.0 .o 27JAN77 10.0 I 2000. o. 22S 370 OELIVf~ PROTECT ~ATLS 21AUG7b 75.0 .o 211FE877 113.0 I 3500. o. 2'10 II be; FAH & {JEL IV~k "'ILLo~ORK 21AIJG7b 120.0 .o 12JUN77 17f>.O I bOOO. 2&11 II !IS uELtVFk MISC RLOG EQUIP o • 21AUG7b 90.0 .o I 9JIIL 77 243,0 I bOOO. o. 2&5 no F TGS ~ PLioiTHS biO be!O 2tAIIG76 t&.o .o SSEP7b •o I 4500. o.OfLIVFW & INSTALL STOR'"I DRAINAGE 21AUG7b bO.O .o 1MAY77275 21111 ~ASMT FNO, 194.0 } 10000. o. SLAB, RMS 2bAUG7b 14.0 .o 9SEP7b 1.0 I 3000. o. FIGURE 33 CONT. lAM PROJECT CONTROL SYSTE14 DATA DaTE 1 JUL 1& LUMP SliM COST REPORT • • RUN !lATE Jill 7b • • RUN SEfiiiENCE 0 NET~O~K 10 111 TITLE OA OISPENSARY•LACKLANO AFB TX MONTEOON CONSR FROM JUL 7& TO 14 AUG 11 PAGE 3 SEOIIF.NCE t:: S ORGANIZATION ACTUAL STANT NEMAI t>E~CIIIT FINISH I ESTIM D ~ I DATE OUR AT COI'IPL l OATE FLOAT I COST COST T•D WI 0 E S C R I P T I 0 N 3UUG7& 120.0 .o 10MAA17 12,0 I 9000, o. 185 34"i OELIVER BLDRS HAROWARE 3UUG7& 30.0 .o 24MAR17 17&,0 I o. o. 1'15 385 DELIVEW LATH & PLASTER MAlLS 3UUG7& 1'50.0 .o 1714AY17 110.0 I 41000. o. 210 11110 OfLIVE~ PLUMB & MECH EUUIP & FIXT :5UUG7& 120.0 .o 14JUN17 1&11,0 I 23000. o. 21'> 450 OfLtVfR ELECT FIXT & EOIIIP :5UUG7& 45.0 .o 3MAY17 201.0 I o. o. 230 430 DELIVER PAINT MATLS 2&1,0 I 1500. o.llbO DELIVER VINYL WALL COVERING 3UUG7& &o.o .o 19JUL11 23&,0 I 3500. o. 235 3UUG7& 45.0 .o 7 JUNH 2115 1170 DELIVER RESILIENT FLOOR MATL 97,0 I 4500. o. 'iSEP7& 90.0 .o 1OMAR77 1qo 311'5 FAB & DEL ALUM ENTR & MTL DRS 5SEP7& 90.0 .o 1&JUL77 225,0 I 4000. o. 2115 1125 OELJVEW TOILET PART & ACCESS bSEPJ& 30.0 .o 50CT7b ,0 I 10000. o.GRADE BEAMS 4500. o. 270 300 CJSEP7b 21 •.0 .o 30SEP7b 1.0 I 280 285 BASMT WALLS ll APR77 1&4,0 I 9000. o. 1"iS£P7& 4'5.0 .o 200 1105 DELIVER CERAMIC TILE MATLS IJJUL 11 148,0 I 1b000o o. 250 1165 l'iSEP7& 111o.o .o 28JUN77 107,0 I DELIVER CASEwORK 15SEP7b 1'50.0 .o 43000. o. 255 11'10 DELIVEW HOSPITAL & MJSC EQUIP 30SEP7b 2.0 .o 24JAN77 115,0 I o. o. 175 Be; SAMPLE ~ASOIIIRY PAN~LS 50CT7b 1,0 I 1soo. o. 30SEP7& 5.0 .o 285 300 OAMPPROUFING 1MAY77 1&9,0 I ·1000. o. 30SEP7& 45.0 .o b1<' bt"i OUTSIDE PLU~BI~G 90.0 .o 1MAY77 124,0 I 24000. o. 30SEP7& b12 b1CJ OIITSIOl ELE.CTRICAL 50CT7b .o .o 14JAN77 101,0 I o. o. 3110 30<; R 10.0 .o 150CT7& • 0 I 4500. o. F~~ & GRADE UNOER ~LOG bOCT7& 900. o. 300 310 10.0 .o 211J A~l77 101,0 I fJOCT7& 305 33'5 8SMT STEPS ~ LNOGS 20.0 .o 4NDV7fJ ,0 I lliiOO. o. 30l UNPR FLR MECH & ELECT R•l 1&0CT7& o. 310 315 51~0V7b 50.0 .o 240EC7& ,0 I 17500. 315 320 FPC PAN SLARS & dMS '50.0 .o 24DEC1fJ ,0 I 27000. o. 0'1 70l UNOR FLR MECH & ELECT R•l 5NOV7b o. I 315 325 13fiOV7fJ .o .o 1MAY77 1&9.0 I o. 0 •.N b15 &20 R .o .o 2bJUL77 255,0 I o. 1--' 1~NOV7b o. &15 f>50 k 2110EC7b .o .o 2110EC7b .o I o. o.320 ~25 R 2'iOEC7b 18.0 •o 24FE!H7 114,0 I 5500 • o. 320 J70 CONC TOPPING FILL 250EC7b &3 .• 0 .o 7APR77 41,0 I 20000. o. 320 37<; ELECT ROUGH•IN 7APR77 34,0 I 21000. 320 3CJ'i MECH ~ PLUMS ROUGH-IN 25DEC7& 1o.o .o 29DEC7b ,0 I 1ooo. o. ~ METaL BUCKS 25DEC7b s.o .o o.325 330 lRECT STL COLS 280EC1fJ .o .o 1MAY17 1211,0 I o. b1CJ f>20 R 2f>JUL 11 210,0 I o. o. 211DEC7& .o .o o. blq b':lO R 2CJUEC7b 42.0 .o l2JlJIII77 124,0 I 13500. b20 b25 SUBGRAOE & BASE FOW PAVING 2qoEc7& .o .o 211JAN77 2&,0 I o. o. HO H"i 300EC7b 10.0 .o IIJAN77 ,0 I 3500. o. Bo 3':10 "EkECT STk STL & JOISTS 30DEC7b 27.0 .o 101'4AR77 44,0 I 9500. o. HS 3110 fXTFRIOk MSNRY WALLS 300EC7& 3,0 .o 27JAN77 2&.0 I o. o. HC, JbO TIME LAG 2JAN77 t4 .o • o 1OFE817 2&,0 I 500• o. 3&0 3&"1 1'-IST ~TL WINOOwS CJJAN77 12,0 .o 20JAN77 ,0 I 9500. o. 350 3':1'i tWOF I)E CK Wl:'=l ,_.'"d ::t> c .1> (IQ 1--' FIGURE 33 CONT. CXll'Jl 0' I .!> Wt>j ...... "0 I~M PROJECT CONTROL SYSTE~ >c: .c-. RUN DATE I JUL 7& • • LUMP SUM COST REPORT ()q ...... • • DATA DATE 1 JUL 76 V1 00 IAUtl SEQUENCE 0 NETwi'JRK ID III TITLE DA DISPENSAAY•LAC~LANO AF8 TX MONTEDON CONSA FAON 1 JUL "' ...... 76 TO 14 AUG 77 ISEQIJENCf E S ORGANilATION .c-. PAGE II Iii I WI START REMAI PERCNT FINISH I ESTIM 0 0 E S C A J P T J 0 N ACTUAL DATE OUR AT COMPL T DATE FLOAT I COST COST T•O3'5'5 36'5 ROOFING & SHT MTL 340 21JAN77 21.0 • o 10FEB77 34'5 A • 0 I 16000• o • 340 500 R 2'5J AN77 .o • o 1OMAM77 44.0 I o. o • 340 &45 A 25JAN77 .o • o 23JUL77 179.0 I o • o. 34'5 385 INST MTL ORS & ALUM ENTR 25JAN77 .o • o 24JUL77 teo.o r o • o.2&JAN77 u.o .o 24MAR77 500 '510 INST DOOR CANOPIES & SIGNS 44.0 J 2000. o. 2&JAN77 to.o • o 2AUG77 &2'5 &30 CURR & GUTTER 179.0 I 500. o • 3&5 370 R CJFE877 21.0 .o 3JUL 77 124.0 I •ooo. o.3&5 38'5 R IOFEB77 • o .o 24FEB77 14.0 I o • o.10FEB77 3&'5 39'5 AC DUCTWORk • o • o 24MAR77 42.0 I o • o • 370 390 11FEB77 5&.0 • o 7APR77 .o I 23000• INTERIOR PARTITION o. 385 190 11FEB77 42.0 .o 7APtH7 111.0 I 17000. STUCCO o. 37'5 395 11FE877 14.0 .o 7APR77 42.0 1 2000. R o. &30 25FEB77 • o .o 7APR77 41.0 I &35 WALKS o. o • &30 &4'5 ASPHALT PAVING 2MAR77 21.0 • o 24JUL77 124.0 1 4000 • o. &35 &4'5 R 2MAR77 to.o .o 24JUL 77 135.0 I &500. o. 'iO INST MECH EllUJP .o I 3900. o. 4MAY77 70.0 .o 2&JUL 77 114'5 4'50 R 14.0 I '5000. o. 44'5 4'55 A 31MAY77 • o •o 14JUN77 14.0 I o• o• 44'5 4&0 A 31MAY77 .o •o 2bJIJN77 z&.o I o• o. 44'5 4&5 A 31MAY77 • o .o 1CJJUL 77 49.0 I o• o. 1145 470 R 31MAY77 .o • o 12JUN77 12.0 I o • o. 445 soc; 31MAY77 .o .o 7JUN77 1.0 I o. n. 'SOX COMP PAINT ~ FIN 1JUN77 4'50 f>50 INST ELECT FIXT ~ EQuiP 4'5.0 .o 15JUL77 • o I &500 • o. 45'5 I JIJN77 42.0 .o c?&JUL77 14.0 I 3000. fl'50 INST PLUMB ~ MECH FlxT o. 4b0 510 VINYL ~ALL COVER I JUN77 30.0 .o 2bJUL 77 2&.0 I ?'500. o. 1JUN77 14.0 .o 2AUG77 49.0 I 1000. o. FIGURE 33 CONT. IBM PROJECT CONTROL SYSTEM RUN DATE JUL 1b * * LUMP SUM COST REPORT * * DATA DATE 1 JUL 76 RUN SEQUENCE 0 NETwORK ID Ill TITLE DA DISPENSAAY•LACKLAND AFB TX MO~TEOON CONSA FROM JUL 76 TO 14 AUG 77 PAGE 5 SEQUENCE E S ORGANIZATION W I STAAT AEMAI PERCNT FINISH I ESTIM 0 ACTUAL ----------------------~--------------------------------------------------------------------------·--------------------- 0 E S C A I P T I 0 N DATE OUR AT COMPL T DATE FLOAT I COST COST T•D WI IJUN77 lb.O .o 28JUN77 12.0 I 1500. o. 4b5 475 INST 501 MILLWORK IJUN77 21.0 .o 28JUN77 1.0 I 1500. o. 47Q 480 AESIL FLA o• o. 1ftJUN77 .o •o 28JUN77 12.0 I 475 480 A I 5JUL 77 13.0 I 1500. o.475 505 COMP MILLWORK 17 JUN77 I boO .o o. 21JUN77 • o .o 9JUL77 18.0 I o• 480 485 A 21JUN77 • o .o 28JUN77 1.0 I o• o.480 490 A 21JUN77 .o .o I 9JUL 77 28.0 I o. o. 480 495 A •o 2AUG77 39.0 I o • o. GOV'T TEST X•RAY PROTECT 22JUN77 3.0 480 510 .o 2AUG77 111.0 I 3000. o. 485 510 INST CASEWORK 22JUN77 24.0 0. INST HOSP & MISC EQUIP 22JUN77 35.0 .o 2AUG77 1.0 I 4000. 490 510 2AUG77 28.0 I 8oo. o. 495 510 INST MISC BLDG EQUIP 22JUN77 14.0 .o 14.0 I 30D-O. o. 13JUL 77 14.0 .o 9AUG77 b50 b5'5 TEST MtCH & ELECT I&JUL 77 18.0 • o 2AUG77 .o I 2&D-O. o• 505 510 201 PAINT & FINISH o.510 b5'5 CLEAN•UP BLDG 3AUG77 1.0 •o 9AUG77 .o I 1000• o. &55 bbO SELL J08 10AUG77 s.o .o 14AUG77 .o I tooo. T 0 T A L 600000. o. -----------------------------------------------------------------------------------------------------------------------· 0\ TOTAL PROJECT ACTUAL COST TO DATE I o. TOTAL PROJECT ESTIMATED COST S 600000. I END OF REPORT N w I wt>:t ..... '"d e-~ ~ OQ ...... (I) VIti colCJl 0'1~ FIGURE 33 CONT. (I) I ~ t;d1-'Ill ~ EP 415-1-431 Aug 86 CHAPI'ER 7 UPDATING Qpdat1ng as the Work Progresses. a. General. Although great benefit can result from planning a job by network analysis, even greater benefit can come from the use of NAS as the job Since the original activity time durations are only estimates, progresses. actual times involved in activity accomplishment will vary as the work progresses. This can be due to any of a number of causes which can and will arise and cannot alwEzys be foreseen. The initial plan can help get the job organized and scneduled, but as various activities actually take more or less time than originally estimated, control of the work is lost unless the network analysis is updated to evaluate the status periodically. Updating the system is necessary to monitor progress, to evaluate impact of delEzys and changes, and to adjust planning so as to meet the required completion of the work. The principles of updating involve substitution of actual occurances in lieu of previous estimates, revising the logic where necessary to reflect changes or to correct previous errors, and then making a new analysis. For example, updating information would include actual start and finish dates which have occurred, revised duration estimates for activities for which better information is available, and addition or deletion of activities or change of restraints occasioned by changes in the work. Updating can be done either manually or by computer. Both techniques are discussed below. In either case, accurate realistic input information is vital to gain a useable update report. b. Manual Updating. Normally analysis based on updating is done by computer, however, manual posting and updating mey be done, if desired, and it is often used on summary diagrams for displEzy and briefing purposes. On an arrow diagram this is usually accomplished by coloring or darkening arrows completely for completed activities and partially for started but not completed activities. Actual finishes and starts are entered at the head and tail of the arrow respectively as shown on Figure 34. A similar notation can be used on a In either case time scaling is not absolutly precedence diagram if desired. necessary. If an actual start cannot be verified, no date earlier than the date of the update should be assumed for an early start as shown by the earliest start possible (ESP) of 120 on Figure 34. Using the actual start and finish dates and any revised logic or durations deemed appropriate and agreed upon at the monthly progress meeting, a forward pass is made from the last actual start or finish on each path. The result mey be a completion later than, earlier than, or equal to the original completion indicating the project is behind, ahead, or on schedule respectively. In the case illustrated, the project has fallen 7 deys behind the original completion from 410 to 417. The critical path mEzy be identified as described earlier once a backward pass is completed. It mEzy deviate from the original critical path and it will indicate the activities in progress which are controlling the completion as of the update time. Accurate job progress data revisions to logic and durations as well as accurate work status entry is essential in this update process. 7-1 EP l.J15-1-l.J 31 Aug 86 c. Computer Updating. Input information for updating by computerinvolves the same type of accurate agreed upon information necessary for manual updating: actual start dates, actual finish dates, revised duration timeestimates for appropriate activities, and logic changes as and if appropriate.Computer programs differ in some respects. Some programs require a percentage of completion for those activities started but not yet finished. The particular requirements of the computer and program being used should be understood before updating is undertaken. An example of updated monitor printouts is shown in Figure 35 for i-j sort, Figure ~ for early start sort, Figure 37 for late start sort, Figure 38 for total float sort, and Figure 39 for lump sum cost reports. Notice that actual start and finish dates are indicated by the letter A in the appropriate column. This program indicates the update date at the beginning of each sort. In addition these printouts indicate such information as earliest and latest delivery dates of materials, dates subcontractors are needed on the job and early and late parameters for Government actions such as approvals. (1) Figure 38, the total float sort (sequence F FL for IBM). In thiscase, as of 28 October 1976 the project completion has slipped from 1l.J August1977 to 21 August 1977 which is most easily seen on this sort. Note that thisprojection appears in the early finish column for activity 655-660 but that thelate finish has been locked at 1l.J August 1977 (Sl.J) generating a -7 float on themost critical path. If the projected completion is earlier than 1l.J August 1977a positive value of float would be indicated on the critical path. Thenegative float indication reveals, that seven days must be regained inaccomplishing the activities remaining on the critical path if the targetedcompletion of 1l.J August 1977 is to be realized. In addition a parallel pathindicates -l.J days total float which must also be regained. It is evident howeasily a NAS updating such as this reveals where and why a project is behindschedule and directs the manager's attention to decisions that must be made to regain schedule. Note that should the update reveal that the cause of the project being behind is excuseable under the contract, the appropriate actionmay be to extend contract completion and release the targeted completion accordingly. (2) Figure ~' the early start sort. Once past the actual starts thebrackets indicate the activities which can start during the remainder of October 1976 and November 1976, the next month. The large number of activities indicating 28 October 1976 early start (data day 120) represent activitieswhich could have started earlier but apparently did not. This program restricts early starts to the date of the update or later unless an actual(Code A) entry is made just as the ESP of 120 was used on the manual update. (3) Figure 37, the late start sort. The bracketed activities are thosewhich must start in the remainder of October and November 1976. ( l.J) Figure 39, the lump sum cost report. The actually completed activitieswith a dollar value and percentage of the value of actually started activitiesbased on expired duration over total duration are entered in the Actual Cost toDate column and summed to attain an earned p~t of $117,630. 7-2 i90 RFP TO USE SOME G F t-IOSP EQUIP .., ·~3f91 NE:60 C 0 #1 *"* *"* 11f~I)S117 DE.LIV GCo T FL ~N HQ',f·~•_.u"'''"-"--- {2401 ESP§ .~<'i~ \- 'iEcL JMBI"'t.T_o ~<) ~-· 8 f' ~MtJ ~ 222 '7-----GUTSI.JE tLECTRICAL 600 ~{...f I I ,.... \ ~ '24,000 l 31 I st.AM,. "''s~ e or-, Euu'P o~ 66 \ cov'r APPROv MISC BLDG EQUIP ESP~ 1 .~m ~ \~ 120)-f-e4t _ I RESUBMIT HOSP 146 ,..;_&_O) 26 I SJBMIT H(JSP TAL 8 MIS( EQ•._,·p ~0 140 116 UII~C EQI.iiP 146 G•JV T APPROV HOSP B MISC EQUIP 145 ~ I I +4{H.~ ~01 141 1.301 E s P G]; '5 IS~BM T s~ ~wv-'.A'~E ""G"'" G'J'v r APPROV CASEWORKI ~tee, +~~ t-f--» 90 135 91 ua 2 1 L52 I s_BM • REc, u,· st.MP_Es s~ 83 GIJV T APPROV B COLOR SEL HE Si-lENT FlG0H 130 I ~ '""'''>~ :2 J suBM r SH DI'IGS MIL, ,.,.ORK 42 43 GOV T APPROV MILLWGRK ~6 2 ~ I ~ 125 fMt 35 / •AM IT t;t., 1 : L--'EJ..i,r-.,G 66 APPHOV SEL I ,.~nL 6') GOY T COLOR VINYL 120 I --~50 I I '3U8Mr~ p:, .... ',A""f '-~ e~ 115 81c._,CJ,i T TEST a (JISAfi--RC.uE P.AI'H 116 110 HE:;,'8MIT Pll.l'·' PAINT I ~~~ ~ ~ (15) 13(.;1 E.SPI21 ~'4395 2G I ','!~M • 8 :,pppr_. ~t.r. "-1[') 8 <:, 0'.0. DEL·>''-~OCP (;,•, )P 1E'3 8 S•Gr<.S ~ 395 320 I ~-t-3*-110 7~ -S 2.00(' 500 I I<'.-, E [ E c~ IN ;g: I 1631 RA< 45 I ,, sv ~ ~ "~'. T[ \ T •,N MECH 8 PLUMB IN 218 ROUGH 1 ++er _, 170) , ?1.ooo I ' 42 S.·8~' PVC' 8 S>-+c-et -' 5 !i'B+ ~ {"51 3.500 IOO 73 GO> • :,DPRGo RQGf 8 S>-EC~ MATL'-'S'---i--------------, r 9 o 95 I -f+":rt ,900~ ~ ~{85) CO"< : 70 ~B ~.E, ,('< .... ISC "'~T'i:.;CS 85 )! /'""------, F-*Q1 (8'1) '12 :) •lJ El t,P<'"' w ~ M 4 j (.,NI'l. ...A~ L s 4 oi-U-'JEL'V,E:OI M4SONFh SM')~'J"~~ !>f ( 175) ?I 3 {S('A~P:_E M4SONRY PANELS / 1 I 48 -J~~H ~l•""(.,~ M' ,..,N[,:"WS AI 45 82 G~ 4PPRQV Mll WINDOWS 'Lt! t'34U~ 6 DELIVER METAL W~~~~~~ 46 5 0 ,. HARD,..."-RE ro ........... c.ov T APPROv p~oR~ 1 HARDWARE /-60 d : ~01 1•201 50 1 1 1 i:! 11, r.;. .'III'V'• n, '"" I'" H 8 M' 5 ~ 31 GOV~ APPRO/ ALvM EN"R 8 MTl DOORS 45 4 r:~, a DEl ALUM ENTR 8 M$T4L.!:iO~RS '35 4 190 1 ESP.§: ~~ f:l ~·,. 8 l'ciiO'f io< FlO 81 GOY T APPRO~ cA'H 8 PLASTER 95 244 DELIVER LATH 6 PLASTER MAlLS •-<.!.. 60 ~ 195 ~OI ESP IZO t'!'l '-<11 I!HII""'I •,,, lO 65 71 GOV' APPRO\! CER "•LE 6 lO\OR SlL 95 247 DELIV(R CERAMI( TILE MATLS 200 ,_...,, HB+ 145) {~t $9,000 ESP~ jO '•1',::1 1 1111111 f'AHlllll'"''· !.\ 4ldS'-(1RI(';o /(l 70 72 G~ ;;.;R 93 )-'''-''"''-----1 1 205 " ' ':.~··~pg;'l•~fl 6 "'l·" '·•' 6 !i.,i\.11' ~~~ 7 !'l 38 G-·.~ AI'P~O~ PLUMB 6 M[CI-I Fl~~ 6 EQJIP 66 ZIO 75 '~~5L~~E 1 I;· '· c•~~ • .,\Ll)' '''' l\ l:,IL"" <'~',~<"9 c.,u..rur APPRoy fLE(I FIJ'il o fOU~P !:i~~ 60 I 11 111 EP 415-1-4 31 Aug 86 SJ8GR.IIQE A'-0 BASE_ FQR P.llli''-G s' 3,50 ~ ;y6 ' ~ )P)::; 6 F.._£ ~;:.~)~G ----------, DEL'\IER 1901 BLDG fQurP 56.000 DEL·IIER HQSP·T.IIL B ~\ M•SC. [QurP S230GG~ 356 \ \ DC vER 1•'>0 C.ASE'I-IOI'Ir<. l.6.00C Rf c,,._ ·f'-T FcOOR MATL s 3.500 8. O[l 1\IER MILL WQRJ( '6.000 WALL COVER 5 :,500 :'£. V[R PAINT MAT L C, I INSTAL'. JOOR Cli.NQPrES [ESJ~"'r;;; \~ 6 SIGNS 5 "lDQ 224 I NOTE: ESP=EARLIEST START POSSIBLE CHANGE ORDER No. I a 120 DAY UPDATING SOLUTION DELIVER 7JIL[ T ACCESS 14,000 MONTEDON CONSTRUCTION CO. PLUMS 6 M[CH EOu•P 6 FIXT CONTRACT NO 999 43 ,OOC DISPENSARY DEL•V[R 6 EQUIP LACKLAND A F 8, TEXAS 123 coo ',UfiM•TTEO BY ~ ..-_:::;~--~- OAT[ /f~'T' ~ECOMME NDFO !IT .,12t2;i -1!--,..tJ_.. ~A QATf ,u~'1' APPA()Iiffl SY ,::£ I!Jt?~-,~tf..#' QAT£ '"~'T6 3-7 FIGURE 34 7·3 IRM PROJECT CONTROL SYSTEM DATA DATE 28 OCT 76 RUh OATE 28 OCT 76 * • !i C ti E 0 II L E R E P 0 R T • * RII'J Sf()tJENCF n NfT•vOJ.II( TU 111 OA OISPENSARY-LACKLANO AFB TX MO~TEOON CONS~ F~QM JliL 7& T(l SEP 71 PAGE SEfJllENCF 1-J TOT S T A R T START F I N 1 S H FIN CAL FARLY LATE FLOAT EARLY LATE FLOAT (I l ( J) 0 E S C R I ~ T 1 0 N OIIIUT 1 • 0 7 1 1JUL7b A 1JUL76 0.0 1JUL76 A IJUL 76 o.o "i I\ITP Q,O 71 4JUL7b A 4JUL7b 0.0 12JliL76 A 12JUL7b o.o MOR -' LAYOUT5 10 APP MECH & ELECT ROUGH-IN MTLS ~I. 0 71 5JIJL76 A 5JtJL7f> 0.0 4AUG76 A 4AUG7b o.o 5 20 SUR -' 5 25 SUS SH DWGS PAN FORMS 21.0 71 10JUL7b A 10JUL7b 0,0 30JUL7b A 30JUL7b o.o 5 10 SUB SH DWGS 4ETAL OOOW BUCKS 20.0 71 21JUL7b A 21JUL76 0,0 "AIIG76 A qAUG7b o.o 1S SUR SH DWGS STRUCT STL & JOISTS. 30.0 71 qJUL76 A qJUl76 0.0 7AUG76 A 7AUG7b o.o"5 40 SUR -' APPWOV MASO~RY MAlLS 4b,O 71 12JUL76 A l2JUL76 0,0 2bAUG7b A 26AUG76 o.o 5 4') SliP SH DWGS MTL tllNDOWS 34.0 71 11AUG7b A 17AUG76 0.0 1qSEP76 A 1qSEP7b o.o 0,0 1ROCT7& A t80CT7f> o.o -t 50 SUR LIST ~ SAMPLE!i ~LORS HAWOt~AWf 65,0 71 15AUG76 A 15AIIG76 I " A 30JUL7b o.o " Vl 55 <;uR SH Dt~GS ALUM ENTR & Jo.ITL OOOW~ 2q,0'71 2JUL7b A 2JUL76 0.0 30JUL76 ':! bO SUR LATH & PLASTER 46,0 71 liAliG76 A 4AUG76 0.0 18SfP7b A 18SEP7& o.o 5 h5 SUB CERAMIC TILE llb,O 71 25JIIL7b h 25JIIL16 0.0 RSEP7b A 8SEP7f> o.o c; 70 SURMIT TOILE. T PART IT IONS & ACCf SSOR IES 41,0 7t 30JUL7b A 30JUL76 0,0 8SEP7& A 8SEP76 o.o " 75 SUBMIT PLUM6 & MECH FIXT & EQUIP 30.0 71 qJUL76 A qJUL7~ 0.0 7AUG76 A 7AUG7& o.o 27,0 7t 2JIJL 7b A 2JUL7b 0.0 28JUL7& A 28JUL76 o.o ':! 80 SURMIT ELECT FIXT & EaUIP ') ~5 SUR -' APP SH OWGS MISC METALS 36.0 71 30JUL76 A ~OJUL7~ 0.0 3SEP76 A 3SEP7& o.o 5 qo SUB -' APP SH O~GS REINF STL 25,0 71 2JUL7b A 2JUL76 0.0 2~JUL7& A 2bJUL7& o.o SH OWGS 46,0 71 6JUL76 A &JUL76 0,0 20AUG76 A ?0AUG7& o.o " q5 SURM1T & APPAOV RuOF DECK '> 100 SURMIT WOOF ~ SHEETMETAL SHOP D~GS 31.0 71 11AUG76 A 11AU~7& 0.0 10SEP7& A 10SEP76 o.o Wt:tl 0.0 13SEP76 A 13SEP76 o.o 1-''"C 5 105 SUAMIT x-~AY P~UTECTION b?,O 71 14JIIL76 A 14JUL76 POOI-I CA~JOP YES -' S I r;w; 4<;,0 71 2&JUL7b A 26J;JL76 0.0 8SfP76 A 8SEP7b o.o >s:: -1:" ':> 11 0 SuRr-tTT II APPRUV (JQ ......Vl CXll 0\ ...... I-!:"- FIGURE 35 SEDtlftlCE l•J PAGE ~ TOT (J) S T A R T START ( J) DESCRIPTION DURAl CAL EARLY L-rE F I ~ I S H FIN FLOAr EARLY LATE FLU AT -----------------------------------------------------------------·----------------------------------------------------w ~ ~ II~ SUBMIT PAINT SAMPLES ~~ 31.0 71 l'IAIIG7b A liAtJG7& 0.0 !8SEP7b A 18SEP7& o.o5 120 SURMIT viNYL ~ALL COVE~lNG 31.0 71 ~~ 4AUG7& A 4AUG7& 0.0 3SEP76 A 3SEP7& o.o ()Q ~ V1 5 125 SURMfT SH D~GS MlLLWOR~ OOI 31.0 71 12JUL7b A 1?JUL7b 0.0 11AUG7& A 11AUG7& o.o 0'\ ...... 5 llO SUHMIT RESILIENT FLOOR SAMPLES ~ I 31.0 71 21AIIG7b A ?lAUGH• 0.0 20SEP7& A 205EP7b o.o') ~~~ SURMIT SH D~GS CASE~OR~ 4&.0 71 !UIJG7b A 111AUG7& 0.0 28SEP7& A ?8SEP7& o.o'> 1~7 C.O. TO USE Stlloll GOV FlJRN HQSP EQUIP I • 0 71 28SEP7b A ~tiSEP7& 0.0 28SEP76 A 28SEP7& o.o~ 140 SURMIT HOSPITAL & MISe EnuiP 45.0 71 i&JUL7b A 2bJUL7& 0.0 8SEP7& A 8SEP7& o.o5 145 SURMIT MISC RLDG EOUIP 35.0 71 31JIIL7& A 31JUL7& 0.0 3SEP76 A 3SEP7& o.o5 I')O CONC DES MIX 1&.0 71 &JUL7b A t>JUL7b 0.0 21JUL76 A ~tJUL7& o.o5 330 PRE-QUALIFY ~ELDERS ti'I.O 71 20AUG7b A 20AUG7b 0.0 lf>NDV7& ~'IOEC7f> 43.05 bOO SUR & APP SH OWGS OUTSIDE ELEC & PLUMR 47.0 71 &JUL7b A &JUL7& 0.0 21AUG7& A ~lAUG7& o.oIll 15 ROtHiH GRAD & EKCAV ~LOG 15.0 71 l&JUL7b A lbJUL7b 0.0 30JUL7b A 30JUL7b o.oI 0 &OS DEMOL ~ SITE GRAOING B.O 71 18JUL7b A 18JUL7& 0.0 1'1AUG7& A t'IAUG7& o.o15 IS~ R -...J o.o 71 30JUL7b I A lOJUL7b 0.0 30JUL7& A 30JIJL7fl o.o0'\ !5 265 R o.o 71 30JUL7b A 30JUL7& 0.0 30JUL76 A 30JUL76 o.o 20 !55 DEL MECH & ELECT ROUGH-IN ~TLS INITIAL 10.0 71 5AUG7& A SAUG76 0.0 J4AUG7& A 14AUG76 o.o25 1~0 GG~•f ~~~RO~ PAN FO~MS 1&.0 71 4AUG7b A IIAIJG7& 0.0 J'IAUG76 A I'IAUG7& o.o30 !&5 GUV'T APPROV MTL DR RuC~S 12.0 71 !0AIIG7b A IOAUG7& 0.0 21AUG76 A 21AUG7fl o.o35 !7ll GOV'T APPROV STR ~TL ~JSTS 18.0 71 8AIIG7& A 8AUG7& 0.0 25AUG7& A 25AUG76 o.o40 17~ DELIVER "'ASONRY MAlLS 1!0.0 71 ?bAUG7b A 2bAUG7& 0.0 13NOV7& 22JAN77 70.045 180 GUV'T APPROV MTL ~I~DO~S 15.0 71 20SEP76 A ?.OSEP7& 0.0 40CT7& A 40CT7& o.o 50 1115 GUV' T APPHOV ~LORS HARO•IARE lO.O 71 l'IOCT7b A I'IOCT7& 0.0 17NOV7& 10NOV76 -7.055 l'lO GOV'T APPROV ALUr~ tiJTR & MTL DOORS I 5. 0 71 liJIJL7b A liJUL7& 0.0 14AUG7b A 14AUG7& o.o FIGURE 35 CONT. PAGE 3 St•JUF"'C[ I-J TOT S T A ~ T START F I N I S H FIN ( I l (.!) U E ~ C R I P T I 0 N OlJIHT CAL EARLY LATE FLOAT EARLY LATE FLOAT bO 1q5 r.uv•T APPkOV LATH ~ PLASTE~ 15.0 71 1QSEP7b A IQSEP7b 0.0 30CT7b A 30CT7b o.o QSEP7b A 9SEP7b 0.0 30CT7b A 30CT7b o.o b5 200 GUV•T APPkOV CER TILf ~ COLOR SEL ?5.0 71 70 2~5 GUV'T APPkOV TOIL PART & ACCES 22.0 71 10SEP7b A IOSEP7b 0.0 IOCT7b A 1DCT7b o.o 75 210 GOV'T APPROV PLUM~ & MECH FIXT ~ EnuiP 2q.o 11 7AUG7b A 7AUG7b 0.0 4SEP7b A 4SEP7b o.o 80 215 GUV'T APPROV ELECT FIXT & EQUIP 30.0 71 2QJUL7b A 29JUL7b 0.0 27AUG7b A 27AUG7b o.o 8SEP7b A 8SEP7b 0.0 230CT7b A 230CT7b o.o 65 305 FAR & DELIVER MISC METALS 4&.0 71 1q.o 11 27JUL7b A 27JUL7b 0.0 14AUG7b A 14AUG7b o.o qo 150 OEL REINF STL 115.0 71 20AUG7b A 20AUG7b 0.0 t2NOV7b 8JAN77 57.0 qs 350 DELIVER ROOF UECK MAlLS 1()0 220 GUV'T APPROV ROOF & SH~TL SH OwGS 18.0 71 11SEP7b A 11SEP7b 0.0 28SEP7& A 28SEP7& o.o 105 225 GUV'T APPROV X-kAY PROTECT 25.0 71 14SEP7b A 1'1SEP7b 0.0 ~OCT7& A 80CT7b 0.0 2~0CT7b IOMAY77 1Q4.0 t0JAN77 23JUL77 1Q4.0 !\ 11 0 500 OELIVER DOOk CANOPIES ~ SIGNS 75.0 71 0.0 180CT7b A 180CT7b o.o 115 11b r.ovT TEST ~ OISAPPROV PAI~T ~o.o 11 1QSEP7b A 1QSEP7b 108.0 11 b 117 RESU~MIT PAiNT SAMPLES 15.0 71 180CT7b A 180CT7b 0.0 tNOV7b t7FE877 30.0 71 2NOV7b t8FEB77 108.0 1DEC7b \QMAR77 108.0 11 7 23u RETEST ~ APPROV PAINT A 4SEP7b 0.0 18SfP7b A 18SEP7& o.o 120 235 GUV'T APPROV COLOR SEL VT~YL WALL COVERING 15.0 7l 4SEP7b 125 240 GUV'T APPROV MILLWORK 14.0 71 12AUG7b A 12AUG7b 0.0 25AUG7b A 25AUG7& o.o A t30CT7b o.o 130 245 GOV'T APPROV ~COLOR SEL RESILIENT FLOOR 23.0 71 21SEP7b A 21SEP7& 0.0 130CT7b 250 GUV 1 T APPkOV CA5E~ORK .:!8.0 71 2QS[P7b A zqSEP7b 0.0 2&0CT7& A 2bOCT7b o.o 13'.> 25.0 71 2QSEP7b A 2QSEP7b 0.0 210CT7b A 230CT7b o.o 137 138 NtGO C.O. *1 13d 140 R o.o 71 230CT7b A 230CT7& 0.0 230CT7& A ?30CT7& o.o Oll IV GOVT FllfiN HOSP E01JJP 240.0 71 230CT7b A 230CT7b 0.0 \QJUN77 28JUN77 q.O nA 4QO 30.0 71 23UCT7b A 230CT7h 0.0 2tNOV7b 30NOV7& q.o Wl::o::l 1'10 141 RlSUR HOSP ~ MI~C EOUIP 1-'1-t:i 255 GUVT APPROV HOSP & MISC EOlllP 30.0 71 ~2NOV7b tnEC7& Q.O 21DEC7b 30DEC7b q.o !:t> 141 ~ ,p.00 ..... V10010\ ......I ,p. FIGURE 35 CONT. SEQUENCE 1-J II PAGE ---------------------~-·----------------------------------------------------------------------------------------------- (I) ( J) 0 E S C R I P T 1 0 ~ TOT DUAAT CAL S T EARLY A A T LATE STAAT FLOAT F I EARLY N I S H LATE FIN FLOAT Wt:<:l 1-''"0 ---------------------------------------------------------------------------------------------------------------------- :> ~ ~ 1115 2&0 GOV'T APPHOV MISC BLDG EQuiP 25.0 71 11SEP7& A IISEP7& 0.0 28SEP7& A 28SEP7& . 0. 0 I)Q I-' V1 CXll 150 2&5 A o.o 71 111AUG7& A 111AUG7& 0.0 111AUG7b A 14AUG7& o.o 0'-i--' I ~ 150 275 A o.o 71 IIIAUG7& A 14AUG7& 0.0 111AUG7& A l11AUG7b o.o 150 b1(i A o.o 7l 14AUG7& A 14AUG7& 0.0 14AUG7b A l4AUG7b o.o 155 275 ROUGH-IN UNDER BSMT 1<'.0 71 15AUG7b A 15AUG7& 0.0 2&AIIG7& A t'bAUG7& o.o 1&0 315 OELIVER PAN FORMS 51.0.71 19AUG7b A 19AUG7b 0.0 100CT7b A IOOCT7& o.o 1&5 3<'5 FA8 & DELIVER MTL OR BUCKS '10.0 71 21AUG7& A 21AUG7b 0.0 IANOV7& t'4DEC7& 3&.0 170 325 FAR ~ OEL STL COLS 5t.o 11 25AIIl;7& A 25AUG7b 0.0 1110CT7& A t40CT7& o.o 170 330 FAB & DEL STR STL & JSTS '10.0 7t 25AVG7b A t'5AUG7b 0.0 22NOV7& 290EC7b 37.0 175 335 SAMPLE MASONRY PANELS 2.0 71 liiNOV7b 23JAN77 70.0 15NOV7& 24JAN77 70.0 180 3&0 FAR & DELIVER METAL WINDOWS 90.0 71 280CT7b 300CT7b 2.0 25JAN77 t'7JAN77 2.0 185 ]II~ DELIV~R BLDRS HARDWARE 120.0 71 18NOV7b 11NOV7b -1.0 17MAR77 t0MAR77 -7.0 '-I I 190 3115 FAB & OEL ALUM ENTR & MTL ORS 90.0 71 14AUG7b A 111AUG7b 0.0 11NOV7& 10MAR77 119.0 CXl 195 3~5 DELIVER LATH ~ PLASTER MATLS. 30.0 71 280CT7& 23FER77 118.0 2bNOV7& t'IIMAA77 118.0 200 1105 DELIVER CERAMIC TILE MAlLS 45.0 71 280CT7& 2&FEB77 121.0 11DEC7b t 1APA77 121.0 205 11<'5 DtLIVER TOILET PART & ACCESS 90.0 71 280CT7& 18APR77 172.0 25JAN77 I&JUL77 172.0 2111 IIIlO ~ELIVEH PLUMR & MECH EOUIP & FIXT 150.0 71 4~EP7b A IISEP7& 0.0 3tJAN77 17MAY77 10&.0 21~ 1150 DELIVER ELECT FIXT & [QUIP 12!1.0 71 27AUG7b A 27AUG7& 0.0 24DEC7& tiiJUN77 172.0 22CI 355 FAR ~ OtLIV SHMTL & RQOF &0.0 71 280CT7& t'2NOV7& t>5.0 2bDEC7& 20JAN77 25.0 225 370 DELIVER PROTECT MAlLS 75.0 71 28DCT7b 12DEC7& 45.0 10JAN77 211FE877 45.0 2 :to 1130 DELIVER PAINT MAlLS 115.0 71 2DEC7b 20MAU77 108.0 15JAN77 3MAY77 108.0 235 llbO OtLIVER VINYL WALL COVE~ING &0.0 71 280CT7b t'IMAY77 205.v 2&DEC7& 19JUL77 205.0 2111) 11&5 FAR & DELlVE~ MILLWORK 120.0 71 25AUG7b A 25AUG7& 0.0 22DEC7b 12JUN77 172.0 FIGURE 35 CONT. 5 TOT S T A R T START F I N I S H FIN SEQUENCE 1-J PAGE (I) ( J) 0 E S C R I P T I 0 N DUIUT CAL EARLY LATE FLOAT EARLY LATE FLOAT 245 250 255 2&0 2&5 270 275 280 285 300 ....... I 300 1.0 ~05 310 315 315 320 320 320 320 325 Bo 330 335 470 485 490 495 270 300 280 285 300 305 ~10 335 315 320 325 325 370 375 395 330 335 35~ 340 DELIVER RESILIENT FLOOR NATL DELIVER CASEWOR~ DELIVER HOSPITAL & MISC EQUIP DELIVER MJSC bLDG EQUIP FTGS & PLINTHS GRADE SEAMS BASMT FNO, SLAB, BMS BASMT WALLS DAMPPROOFING R F&B ~ GRADE U~DER BLDG BSMT STEPS & LNDGS 30X UNPR FLH MECH & ELECT R-I FPC PAN SLABS ~ 8MS 70X UNDH FLR MECH & ELECT R-I R CONC TOPPINb FILL ELECT ROUGH-IN MECH & PLUMB ~OUGH-IN ERECT STL COLS & METAL BUCKS R ERECT STR STL &·JOISTS EXTERIOR MSNRY WALLS 45.0 71 130CT7b A 13DCT76 0.0 26NOV76 7JUN77 193.0 150.0 71 280CT76 10FE877 105.0 26MAA77 9JUL77 105.0 180.0 71 22DFC7b 31DEC76 9.0 19JUN77 28JUN77 9.0 90.0 71 280CT7b 21APR77 175.0 25JAN77 19JUL77 175.0 15.0 71 14AUG7b A 14AUG76 0.0 28AUG7b A 28AUG76 0.0 10.0 71 29SEP76 A 29SEP76 0.0 80CT7b l 80CT76 o.o 17.0 71 26AUG7b A 2blUG76 0.0 ttSEP7& l 11SEP76 o.o 21.0 71 t2SEP7b l 12SEP76 0.0 20CT76 l 20CT76 o.o o.o 71 30CT7b l 30CT7b 0.0 60CT76 A 60CT76 o.o o.o 71 80CT7b A 80CT7~ 0.0 80CT7b A 80CT76 o.o 12.0 71 90CT7b A 90CT7b 0.0 200CT7b l 200CT76 o.o 10.0 71 280CT7b 15JAN77 79.0 6NOV76 24JAN77 79.0 20.0 71 200CT7b A 200CT76 0.0 8NOV76 4NOV76 -4.0 50.0 71 9NOV7b 5NOV76 -o.o 28DEC76 24DEC76 -4.0 50.0 71 9NOV7b 5NOV76 -4.0 28DEC76 24DEC76 -o.o o.o 71 28DEC7b 24DEC76 -o.o 28DEC7b 24DEC76 -o.o 18.0 71 29DEC7& 7FEB77 40.0 15JAN77 24FE877 oo.o &3.0 71 29DEC7b 4FEB77 37.0 1MlR77 7APR77 37.0 70.0 71 29DEC7b 28JAN77 30.0 8MAR77 7APR77 30.0 5. 0 71 290EC7b 250EC7b -4.0 2JAN77 29DEC7b -4.0 o.o 71 2JAN77 24JAN77 22.0 2JlN77 24JAN77 22.0 10.0 71 3JAN77 30DEC76 -4,0 12JAN77 8JAN77 -o. O" w~ ...... '1::1 27.0 71 3JAN77 12FEB77 40.0 2'1JAN77 10MAR77 40.0 >c:: OQ ~ ....... V1 CXl I 0\ ....... ~ I ~ FIGURE 35 CONT. Wf:l::lf-'""d :>c .p..OQ f-' l..n CXll "' f-'I.p.. '-IIf-' 0 SEQUENCE 1-J PAGE & .( (I) (J) TOT S T A H T START F I N I S H FIN 0 E S C R I P T I 0 N OURAT CAL EARLY LATE FLOAT EARLY LATE FLOAT 335 3&0 TIME LAG 3.0 71 3JAN77 25JAN77 22.0 5JAN77 27JAN77 22.0 340 345 R o.o 71 29JAN77 IOMAR77 40.0 29JAN77 IOMAR77 40.0 340 500 R o.o 71 2qJAN77 23JUL77 175.0 zqJAN77 23JUL77 175.0 340 &45 R o.o 71 29JAN77 24JUL77 17&.0 29JAN77 24JUL 77 17&.0 345 385 INST MTL DRS & ALUM ENTR 14.0 71 18MAR77 11MAR77 -7.0 31MAR77 24MAR77 -7.0 350 355 ROOF DECK 12.0 71 13JAN77 9JAN77 -4.0 24JAN77 20JAN77 -4.0 355 3&5 ~OOFING & SHT MTL 21.0 71 25JAN77 21JAN77 -4.0 14FEB77 IOFER77 •4.0 3&0 3&5 JNST MTL wiNnOwS 14.0 71 2&JAN77 28JAN77 2.0 8FEt:!77 tOFEil77 2.0 3&5 370 R 0. 0 .71 14FEB77 24FEB77 10.0 14FEB77 24FEB77 10.0 3&5 385 R o.o 71 14FEB77 24MAR77 38.0 14FEB77 24MAR77 38.0 3&5 395 AC OUCTWOkK 5&.0 71 15FEB77 11FEB77 -4.0 IUPR77 7APR77 -4.0 370 390 INTERIOR PAkTITION 42.0 71 15FEB77 ?.5FEB77 10.0 28MAR77 7APR77 10.0 375 3QS R o.o 71 1MAR77 7APR77 37.0 1MAIH7 7APR77 37.0 385 HO STUCCO 14.0 71 1APR77 25MAR77 -7.0 14APR77 7APR77 -7.0 390 395 R o.o 71 l4APR77 7APR77 -7.0 14APR77 7APR77 -7.0 390 405 R o.o 71 14APR77 11APR77 -3.0 14APR77 IIAPR77 -3.0 390 420 PLASTER WALLS 14.0 71 15APR77 20APR77 5.0 28APR77 3MAY77 5.0 395 410 CEILG SUSP SYST & INSuL 14.0 71 15A'PR77 8APR77 -7.0 2AAPR77 21APR77 -7.0 405 420 CERAMIC TILE 22.0 71 15APR77 12APR77 -3.0 &MAY77 3MAY77 -3.0 410 430 PLAS CLG 12.0 71 21UPR77 22APR77 -1.0 IOMAY77 3MAY77 -7.0 410 445 ACOUIST & OTHER CEILINGS 35.0 71 29AP~77 27APR77 -2.0 2JUN77 31MAY77 •2.0 420 425 R o.o 71 &MAY77 I&JUL 77 71.0 &MAY77 I&JUL77 71.0 420 430 R o.o 71 &MAY77 3MAY77 -3.0 &MAY77 3MAY77 ·3.0 FIGURE 35 CONT. SEilUENCE 1-J PAGE 7 TOT S T A ~ T START F I N I 5 H FIN (I) (J) 0 E S C R I P T I 0 N OURAT CAL EARLY LATE FLOAT EARLY LATE FLOAT 425 1130 1130 11110 4110 11115 11115 11115 11115 4115 ........ I ,_. 11115 ,_. 1150 1155 llbO llb5 470 1175 1175 1180 480 480 1180 485 510 11110 445 1155 b50 1150 1155 llbO llb5 1170 505 b50 b50 510 1175 11110 1180 505 485 11'10 11'15 510 510 TOILET PA~T ~ ACCESS R 30% PAINT & FINISH R INST MECH EQUIP R R R R R 50% COMP PAINT & FIN INST ELECT FIXT & EDUJP INST PLUMB & MECH FIXT VINYL WALL COVER INST 50% MILLWORK RESIL FLR R CO~P MILLWORK R R R GOV'T TEST X-RAY PROTECT INST CASEWORK 17.0 0 .o 28.0 o.o o.o o.o o.o o.o o.o o.o 70.0 115.0 112.0 30.0 14.0 1b.O 21.0 1b.O o.o 0 .o o.o 3.0 24.0 71 71 71 71 71 71 71 71 71 71 71' 71 71 71 71 71 71 71 71 71 71 71 71 7MAY77 10MAY77 1 1MAY77 10MAY77 11MAY77 7JUN77 7JUN77 7JliN77 7JUN77 7JUN77 8JUN77 8JUtH7 8JUN77 8JUN77 8JUN77 8JUN77 23JUN77 24JUN77 28JUN77 28JUN77 28JUN77 29JUN77 29JIJN77 17JUL77 17MAY77 IIMAY77 2bJUN77 18MAY77 14JUN77 2bJUN77 1'1JUL77 12JUN77 7JUN77 1JUN77 15JUN77 27 JUN77 ?OJUL77 13JUN77 8JUN77 28JUN77 30JUN77 9JUL77 28JUN77 19JUL77 31JUL77 10JUL77 71.0 7.0 -7.0 47.0 7.0 7.0 19.0 112.0 5.0 0.0 -7.0 7.0 19.0 42.0 5.0 0.0 5.0 &.0 11.0 0.0 21.0 32.0 11.0 23MAY77 10MAY77 7JUN77 10MAY77 19JUL77 7JUN77 7JUN77 7JUN77 7JUN77 7JUN77 22JUL77 19JUL77 7JUL77 21JUN77 23JUN77 28JUN77 23JUN77 9JUL77 28JUN77 28JUN77 28JUN77 1JUL77 22JUL 77 2AUG77 17MAY77 31MAY77 i?&JUN77 2&JUL77 1 4JUN77 i?&JUN77 1 9JUL 77 12JUN77 7 JUN77 1 5JUL77 2&JUL 77 i?&JUL 77 2AUG77 28JUN77 i?8JUN77 i?8JUN77 1 5JUL 77 9JUL77 i?8JUN77 19JUL 77 i?AUG77 2AUG77 71.0 7.0 -7.0 47.0 7.0 7.0 19.0 42.0 5.0 o.o -7.0 7.0 19.0 42.0 s.o o.o s.o &.0 11.0 o.o 21.0 32.0 11.0 I.J,.lt%j 1-''"d > c ~ OQ """" l.l1 001 0\ """" I ~ FIGURE 35 CONT. SEQUENCE 1-J PAGE a (I) 490 495 500 505 (J) 510 510 510 510 0 E S C R I P T I 0 INST HOSP & ~ISC EQUIP INST MISC BLDG EQUIP INST DOOR CANOPIES & SIGNS 20l PAINT & FINISH N TOT DURAl 35.0 14.0 10.0 u.o CAL 71 71 71 71 S T EARLY i!9JUN17 i!9JUN17 30JAN77 i!3JUL 17 A R T LATE 29JUN77 20JUL77 24JUL77 lbJUL77 START FLOAT 0.0 21.0 175.0 •7.0 F I N I EARLY 2AUG77 12JUL77 8FEB77 9AUG77 S H LATE 2AUG17 2AUG77 2AUG17 2AUG17 FIN FLOAT 0.0 21.0 175.0 •7.0 wt:r1 1-'"'tt ~~ OQ ...... V1 col Q\1-' I ~ 510 &55 CLEAN-liP BLDG 1. 0 7l 10AUG77 3AUG77 -7.0 lbAUG77 9AUG77 •7.0 bOO bli! DEL MAlLS OS ELEC & PLIJMB 34.0 71 21AUG76 A 21AUG7b 0.0 23SEP7b A 23SEP7b 0.0 b05 &10 R o.o 71 t9AUG76 A 19AUG7b 0.0 19AUG76 A 19AUG7b 0.0 &05 &ti! R o.o 7l 19AUG7b A 19AUG76 0.0 19AUG76 A 19AUG76 0.0 blO &20 DELIVER & INSTALL STORM DRAINAGE bO.O 71 i!80Ci76 3MAR77 12&.0 i!60EC76 IMAY77 12b.O b\2 &15 OUTSIDE PLUMBING 45.0 71 280CT76 18MAR77 141.0 110EC76 1MAY77 141.0 btl &19 OUTSIDE ELECTRICAL 90. o 11 i!80CT7b 1FEB77 96.0 i!5JAN77 IMAY77 9&.0 bl5 1>20 R o.o 71 11DEC7b 1MAY77 141.0 110EC76 IMAY77 141.0 &15 &SO R o.o 7l 11DEC7b 2bJUL77 227.0 11DEC7& 26JUL77 227.0 -...J I ...... "' blq blq &20 &50 R ~ o.o o.o 71 71 i!o:iJ AN77 i!5JAN17 IMAY77 2bi1JL17 96.0 Ui!.O i!5JAN77 i!5JAN17 1MAY77 2bJUL77 9&.0 182.0 b20 &25 SUBGRADE & BASE FOR PAVING 42.0 71 i!bJAN77 2MAY17 96.0 8MAR17 12JUN77 9&.0 b25 &30 CURB & GUTTER i!l.O 71 9MAR77 13JUN77 96.0 i!9MAR17 3JUL77 96.0 b30 &35 WALKS 21.0 71 30MAR77 4JUL17 96.0 19APR17 211JUL 77 9b.O &30 &45 ASPHALT PAVING 10.0 71 30MAR77 15JUL77 107.0 8APR77 i''IJUL17 107 .o &35 &45 R o.o 71 19APR17 211JUL 77 96.0 t9APA77 24JUL 77 9&.0 b45 &55 TOPSOIL & FINE GRADING 16.0 71 i!OAPR77 25JUL77 96.0 '5MAY77 9AUG77 9&.0 bSO b55 TEST MECH & ELECT 14.0 71 i!OJUL 17 27 JUL 77 7.0 2AliG77 9AUG77 7.0 &55 bbO SELL JOB 5.0 71 17AUG77 I OAUG77 •7.0 21AUG77 S4 I4AUG77 -7.0 FIGURE 35 CONT. - IRM PROJECT CONTROL SYSTEM IWfJ DATE .:!8 OCT 7b S C H E 0 U L E R E P 0 R T DATA OATE ?.~ OCT 7b * * * * RUN SfQitENCF. 0 Nl: T•~ORK 10 It! DA DISPENSARY-LACKLANO AFB TX MONTEOOIIJ CONSR FROt-1 JUL 7& TO SEP 77 SEQuENCE E S t'AGE TOT S T A R T START F I N I S H FIN (I) (J) 0 E S C R I P T I 0 N DURAl CAL EARLY LATE FLOAT EARLY LATE FLOAT 5 NTP 1.0 71 IJUL7b A 1JUL7b 0.0 1JUL7& A 1JUL7b o.o 5 55 SUR SH OWGS ALUM EIIJTR ~ MTL DOORS 2Q.O 71 2JUL7b A 2JUL7b 0.0 30JUL7& A 30JUL7& o.o 5 80 SUBMIT ELECT FTXT & FQUIP 21.0 71 2JIIL 7& A 2JUL 7& 0.0 28JUL7& A 28JUL7b o.o 5 QO SuB ~ APP SH DWGS REINF STL 25.0 71 2JliL7b A 2JUL7b 0.0 2&JUL7b A ?bJUL7b o.o 5 10 MOA & LAVUUT q.o 71 4JUL7b A 4JUL7h 0.0 li'JUL7& A 12JUL7& o.o 5 20 SUA & APP MECH & ELECT RflUGH,-IN r-ITLS 31.0 71 '5JliL7b A '5JUL7h 0.0 4AUG7& A 4AUG7b o.o 5 q~ SUAMIT & APPROV ROOF DECK SH OWGS 4&.0 71 bJliL7b A bJUL7b ll.O 20AUG7& A 20AUG7& o.o 1&.o 71 bJLIL 7b • bJtJL 7& 0.0 21JUL7& A ?1JUL7& 0.0 5 150 CONC DES NIX fLEC & PLU~B '17.0 71 bJliL7b A oJUL7b 0.0 21AIIG7b A 21AUG7h o.o 5 nOO SUB ~ APP SH DWGS OUTSIDE 5 35 SUH ~H DWGS STRUCT STL & JOISTS 30.0 71 QJUL7b A QJUL7b 0.() 7AUG7& A 7AU~7b o.o QJUL7b A QJUL7n 0.0 7AIIG7b A 7AUG7f> o.o ...... 5 75 SUBMIT PLUMB & MECH FIXT ~ EQUIP 30.0 71 I - U.l 5 25 SUB SH OWGS PAN FORMS 21.0 7'1 10JUL7b A lOJULJb 0.0 30JUL7b A 30JUL7b o.o 5 40, SUA ~ APP~OV MASONRY MAlLS 4&.0 71 l?.JliL7b A 1i:!JUL7& 0.0 26AUG7& A ?.bAUG7b o.o A 11AUG7b o.o 5 12~ SUBMIT SH OwGS MILLWORK 31.0 71 12JliL7b A 12JUL7n 0.0 11AliG7& 71 14JUL7o A 14JUL7b 0.0 13SEP7b A t3SEP7& o.o 5 105 SUBMIT x-RAY PROTECTION &2.0 15 ROUGH GRAD & EXCAV BLOG 15.0 71 lbJUL7b A 1&JUL7h 0.0 30JIIL7& A 30JUL7b o.o 10 33.0 71 18JUL7b A 18JUL7b 0.0 1QAUG7& A \QAUG7b o.o lll &05 OEMOL & SITE GRADING 5 30 SUR SH DWGS r.tETAL DOOR SliCKS 20.0 71 21JIIL1b A .?1JUL7b 0.0 QAUG7b A QAUG7& o.o 5 &5 SUB CERAMIC TILE 4&.0 71 2'5JUL7b A 25JUL7b 0.0 8SEP7b A 8SEP7& o.o 71 2&JUL7b A 2&JUL7b 0.0 8SEP7& A 8SEP7b o.o 5 110 SUBMIT & APPROV DOOR CANOPIES~ SIGN~ 45.0 5 140 SUBMIT HOSPITAL & MISC EQUIP 45.0 71 2bJIIL 7& A i'&JUL 7& 0.0 8SEP7& A 8SEP7& o.o wtr:~ 1-''"d > c:: ~ 00 1-' \.r1 ool 0\1-' I ~ FICUI;.E 36 Wt:r1 1-'1-d PAGE 2 SEflliENCE l S :> ~ ~ F I N I S H FIN OQI-' TOT S T A A T START -----------------------------------------------------------------------------------------------------------------------V1 LATE FLOAT ( I l ( J) u E S C ~ 1 P T I U N OUAAT CAL EARLY LATE FLOAT EARLY CXll 0\1-' . I A 27JUL7& 0.0 111AUG7b A l4AUG7& o.o ~ 'lO 150 O~L RETNF STL 19.0 71 27JUL7& 29JUL7b A 29JUL7& 0.0 27AUG7& A 27AUG7& o.o 8() 215 GOV'T APP~OV ELECT FixT & EQUIP 30.0 71 5 70 SURMTT TOILET PARTITIONS ~ ACCESSORIFS 111.0 71 30JIJL 7& A 30JIJL 7& 0.0 8SEP7& A 8SEP7& o.o O~GS MISC MfTALS 3&.0 71 30JUL7b A ~OJUL7& 0.0 3SEP7& A 3SEP7& o.o 5 85 SuR ~ APP SH o.o 71 30JIIL7b A 30JIJL 7& 0.0 30JllL7& A 30JUL7& o.o 1'\ 155 Q 15 2&5 R o.o 71 30JUL7& A 30JUL7b 0.0 30JUL7& A 30JUL7& o.o 'J 1115 SURMTT MltiC RLOG EQUIP 3c;.o 11 31JUL7b A 31JUL7b 0.0 3S£P7& A 3SEP7& o.o 55 l'lO GOV'T APPHOV ALUM ENTR & MTL DOORS 1'5.0 71 31JUL7b A 31JUL7b 0.0 14AUG7& A \4AUG7& o.o 4AIIG7& A LIAUG7f> O.o 18SEP7& A 18SEP7& o.o ') bU SUR LATH & PLASTER 11&.0 71 ') 120 SURMIT VINYL ~ALL CUVERIN~ 31.0 71 IIAUG7& A IIAUG7& 0.0 3SEP7& A 3SEP7& o.o 1&.0 71 IIAUG7& A IIAUG7b 0.0 1qAUG7& A 19AUG7& o.o "-.1 2S lbO GOV'T APPROV PAN FORMS I A 5AUG7& 0.0 111AUG7& A 14AUG7b o.o 1-' 20 155 OlL MECH & ELECT ROUGH-IN MTLS INITIAL 10.0 71 5AUG7& ~ 7AIIG7b A 7AUG7& 0.0 IISEP7& A 4SEP7& o.o 75 210 GUV'T APP~OV PLUM~ & MfCH FIXT & EQUIP 29.0 71 18.0 71 8AIIG7b A 8AUG7& 0.0 25AUG7& A 25AUG7b o.o 35 170 GUV'T APP~OV STR STL ~JSTS 30 lb'J r.uv•T APPR0V IHL UR RI)CIIS 12.0 71 1 0AIIG7b A I OAUG7& 0.0 21AIIG7& A 21AUG7b 0.0 5 100 SURt!IT ROUF ~ SHEETMETAL SHOP ONGS 31.~0 71 11AliG7b A 11AUG7& 0.0 10SEP7h A \OSEP7& 0.0 125 2110 GOV'T APPROV MILL~ORK 111.:0 7 1 12AIJG7b J. 12AUG7b 0.0 25AUG7& A 25AUG7& 0.0 11&.0 71 14AUG7b A 14AUG7& 0.0 28SEP7& A 28SEP7& 0.0 "5 I~'J SU~MIT SH O~GS CASEWORK 150 2b'J R o.o 71 111AUG7b A 14AUG7b 0.0 111AUG7& A 111AUG7& 0.0 o.o 71 14AIIG7b A 14AUG7& 0.0 111AUG7& A 14AUG7& 0.0 150 275 R 1511 blu R o.o 71 111AIJG7b A 111AUG7& 0.0 111AUG7& A 14AUG7& 0.0 I 'l ll 3115 FAH '-OE.L ALIIM ENTR 1!. ~ITL OkS 90.0 71 14AUG7& A 14AUG7& 0.0 l1NOV7b 10MAA77 119.0 2&':> 270 FTGS & PLINTHS 15.0 71 IIIAUG7b A IIIAUG7& 0.0 28AUG7& A 28AUG7& 0.0 FIGURE 36 CONT. - SEQUENCE E S PAGE 3 TOT S T A R T START F I N I S H FIN (I) ( J) D t S C R 1 P T I 0 N DUIUT CAL EARLY LATE FLOAT EARLY LATE FLOAT 5 SO SUR LIST & SAMPLES BLDRS HAkDwA~E &'5.0 71 1'5AUG7b A 15AUG7b 0.0 1BOCT7b A IBOCT7& o.o 15<; ?75 ROUGH•TN UNDER BSHT '· i?. 0 71 1'5AUG7b A 15AUG7b 0.0 2bAUG7b A 2&AUG7b o.o 5 115 SliR SH DwGS MTL wiNDOwS 311.0 71 17AUG7b A 17AUG7b 0.0 t9SEP7b A 19SEP7b o.o ~ 115 SUBMIT PAINT SAMPLES .H.O 71 19AUG7b A 19AUG7b 0.0 1BSEP7b A 18SEP7b o.o 1&0 31~ DELIVER PAN FORMS 53.0 71 19AUG7b A 19AUG7b 0.0 100CT7b A t00CT7b o.o &05 &10 R o.o 71 19AliG7b A 19AUG7b 0.0 19AUG7b A 19AUG7b o.o bO<; &12 R o.o 71 19AIIG7b A 19AUG7b 0.0 19AUG7b A 19AUG7b o.o 5 330 PRE-QUALIFY WELDF.~S I:IQ.O 71 20AUG7b A 20AUG7b 0.0 1bNOV7b 290EC76 113.0 Q5 350 DELIVER ROOF DECK MAlLS 8'5.0 71 20AUG7b A 20AUG7b 0.0 12~0V7b BJAN77 'i7.0 'j 110 SURMIT RESILIENT FLOOR SAMPLES 31.0 71 21AUG7b A 2tAUG7b 0.0 20SEP7b A 20SEP7b o.o 1b'.i 325 FAR ~ ntLIVER MlL OR BUCKS 90.0 71 21AUG7b A 21AUG7b 0.0 18NOV7b 240EC7b 36.0 bOO &12 DEL MAlLS OS lLEC & PLUMP 34.0 71 21AUG7b A 21AUG7b 0.0 23SEP7b A 23SEP7b o.o 170 32~ FAR ~ ~EL STL COLS 51.0 71 2'5AUG7b A 25AUG7b 0.0 1110CT7b A 140CT7b o.o 170 330 ~AB & DEL STR STL ~ JSTS 90.0 71 25AUG7b A i?SAUG7b 0.0 22NOV76 ?90EC7& 37 .o -...J I ,_. 2110 lib~ FAB & OlLIVER MILLWORK 120.0 71 25AUG7b A 25AUG7b 0.0 22DEC7b 12JUN77 172.0 U1 110 175 DELIVER MASONRY MAlLS 80.0 11 2bAUG7b A 2&AUG7b 0.0 13NOV7b 22JAN77 70.0 275 280 BASMT FND, SLAB, 8MS 17.0 71 2bAUG7b A 2bAUG7b 0.0 11SEP7b A 11SEP7b 0.0 215 4'50 DELIVER ELECT FIXT & EQUIP 120.0 71 27AUG76 A 27AUG7b 0.0 211DEC7b 14JUN77 172.0 120 235 GOV'T APPRDV COLOij SEL VINYL ~ALL COVERING 1'5.0 71 4SFP7b A 4SEP7b 0.0 1RSEP7& A 18SEP7b 0.0 1115 2&0 GOV'T 4PP~OV MISC RLOG lQUIP 2<;.0 71 IISEP7b A IISEP7b 0.0 2BSEP7b A 28SEP7b 0.0 210 11110 DELIVER PLIIW\ & MEC11 EQUIP & FixT 150.0 71 IISEP7b A 4SEP7b 0.0 31JAN77 t7MAY77 10&.0 8<; 305 FAR & DELIVER MISC ~FTALS llb.O 71 8~EP7b A BSEP7b 0.0 230CT7b A ?30CT7b 0.0 b'5 200 GOV'T 4PPijOV CE~ TILE & COLOR SEL 2S.O 71 QSEP7b A 9SEP7b 0.0 30CT7b A 30CT7b o.o Wtrl ,_.'"1:1 ~ ~ ..,.. (1Q .... U1 00 I 0\ .... FIGURE 36 CONT. I..,.. wtz:l ..-'"d • SEQUENCf E S PAGE II > ~ OQ ~ 17 -----------------------------------------------------------------------------------------------------------------------TOT S T A H T STA~T F I N I S H FIN V1 OOI (I) (J) D E S C R I P T 1 D N OIJIUT CAL EARLY LA Tf FLOAT EARLY LATF FLOAT Q'\ .... I --------------7--------------------------------------------------------~---------------------------------------------- ~ 70 205 GUV'T APPHOV TOIL PART & ACCES 22.0 71 IOSEP7o A 10SEP7o 0.0 IOCT7o A IOCT7b o.o 100 220 GOV 1 T APPROV ROOF & SHMTL SH OWGS 18.0 71 11SEP7o A 11SEP7o 0.0 28SEP7o A 28SEP7o o.o 280 285 BASMT WALLS 21.0 71 12SEP7o A 12SEP7o 0.0 20CT7o A 20CT7o o.o 105 2~5 GOV'T APPROV X-HAY PROTECT 25.0 71 14SEP7b A IIISEP7o 0.0 AOCT7o A 80CT7b o.o bO 195 GOV 1 T APPHOV LATH & PLASTER 1'5.0 71 19SEP7b A 19SEP7b 0.0 JOCT7o A ~OCT7b o.o 115 11& GOVT TEST & DISAPPROV PAINT 30.0 71 19SEP7o A 19SEP7b 0.0 1ROCT7o A 180CT7o o.o 45 180 GOV'T APPROV MTL ~INDOWS 15.0 71 20SEP7b A 20SEP7o 0.0 IIOCT7o A IIOCT7b o.o 130 245 GOV 1 T APPROV & COLOR SEL RfSlLIENT FLOOR 23.0 71 21SEP7o A ?ISEP7b 0.0 130CT7o A t30CT7o o.o c; 137 C.O. TO USE SOME GOV FURN HOSP EQUIP 1.0 71 28SEP7b A ?~~EP7b 0.0 28SEP7o A 28SEP7o o.o 135 250 GOV 1 T APPROV CASEWORK 2R.O 71 29SEP7b A 29SEP7b 0.0 2bOCT7o A 2b0CT7o o.o ~ •..... Q'\ 270 137 300 138 GRADE REAMS NEGO C.O. *I 10.0 ~c;.o 71 11 29SEP7o 29SEP7b A 29SEP7b A ?9SEP7b 0.0 80CT7b 0.0 230CT7b A 80CT7b A ?.30CT7o o.o o.o 285 300 DAMPPROOFIIIIG 4.0 71 30CT7o A 30CT7b 0.0 &OCT7o A &OCT7b o.o 300 305 R o.o 71 ROCT7b A ROCT7b 0.0 80Cl7b A 80CT7b o.o 300 310 F&B & GRADE UNDER BLDG 12.0 71 90CT7b A 90CT7o 0.0 200CT7o A 200CT7b o.o 2115 1170 DELIVER RESILIENT FLOOR MAlL 115.0 71 1~0CT7b A 130CT7b 0.0 2&NOV7b 7JUN77 lq3.0 uo 117 RESUAMIT PAINT SAMPLES 1'5.0 71 180CT7b A ld0CT7b 0.0 1NOV7b t 7FfR77 108.0 ~0 18'5 GOV 1 T APPHOV dLORS HARDWARE 30.0 71 lqOCT7b A 190CT7o 0.0 17NOV7& IOI\IOV7o -7.0 310 315 301 UNPR FLR MfCH & ELECT P-I 20.0 71 200CT7b A ?OOCT7o 0.0 8NOV7& IIIIIOV7b -4.0 138 1110 R o.o 71 230CT7o A 230CT7o 0.0 230CT7o A 230CT7b o.o 138 119C DELIV GOVT FURN HOSP EDUIP 2110.0 71~230CT7b A <>Jncno 0.0 lqJUN77 28JIJN77 q.o 1110 1111 RESUB HOSP & MISC EQUIP 30.0 71 ~230CT7b A 230CT7b 0.0 21NOV7b 30IIIOV7o 9.0 110 '500 DELIVER DOOR CANOPIES ~ SIGNS 75.0 71 280CT7b IOMAY77 1911.0 IOJAN77 23JUL77 194.0 FIGURE 36 CONT. - SEQUENCE E S PAGE 5 TOT S T A R T START F I N I S H FIN (I) (J) D E S C A I P T I 0 N OuRAT CAL EARLY LATE FLOAT EARLY LATE FLOAT -------------------------------------------------------------------------------------------------D-------------------- ...... I ~ ...... :;.:; (!) <: (!) l'i en (!) td I-' Ill ~ 180 360 FAB ~ DELIVER METAL WINDOwS 90.0 71 280C T1b 300CT7b 2.0 25JAN77 27JAN77 2.0 195 31'5 DELIVER LATH & PLASTER MAlLS 30.0 71 280CT7b ?3FE~77 118.0 26NOV76 2414AA77 118.0 200 405 DELIVER CERAMIC TILE MAlLS 45.0 71 280CT7o 2bFE877 121.0 110EC76 1lAPR77 121.0, 205 425 DELIVER TOILET PART & ACCESS 90,0 71 280CT7b 18APR77 172.0 25JAN77 16JUL77 172.0 220 355 FAB ~ DELIV SHMTL & ROOF &0.0 71 280CT7b 22NOV76 25.0 260EC76 20JAN77 25.0 225 370 DELIVER PROTECT MAlLS 75,0 71 2"0CT7b 12DEC76 45.0 10JAN77 24FE877 45,0 235 4&0 DELIVER VINYL WALL COVERING bO.O 71 280CT7b 21MAY77 205.0 26DEC76 1qJUL77 205.0 250 q8S DELIVER CASEWORK 150.0 71 280CT7b tOFE877 105.0 2614AR77 qJUL77 105,0 2&0 495 DELIVER MISC BLDG EOUIP 90.0 71 280CT7b 2tAPR77 175.0 25JAN77 1qJuL77 175.0 305 335 BSMT STEPS & LNOGS 10.0 71 280CT7b 15JAN77 79.0 6NOV7b 24JAN77 1q,o b10 b20 DELIVER & INSTALL STORM DRAINAGE bO.O 71 280CT7b 3MAR77 12b.O 2bDEC7b 114AY77 12b.O b12 b15 OUTSIDE PLUMBING q5,o 11 280CT7b t&MAR77 141.0 110EC7b 1MAY77 1111,0 b12 b19 OUTSIDE ELECTHICAL 90.0 71 21'0CT7b 1FE877 qb,O 25JAN77 1MAY77 96.0 11 7 2lO RETEST & APPROV PAINT 30,0 71 2NOV7b 18FER77 108.0 10EC7b l9MAR77 108,0 315 320 FPC PAN SLABS & RMS so.o 71 qNOV7b 5NOV7b -q,Q 2ROEC7b 24DEC7b -4.0 315 325 70l UNOH fLR MECH & ELECT R-1 50.0 71 qNOV7b 5NUV7b -4.0 280EC7b 240EC7b -11.0 175 335 SAMPLE MASONRY PANELS 2.0 71 14NOV7b 23JAN77 70.0 t~NOV7b ?.liJAN77 70,0 185 345 OtLIVER RLORS HAROWAHE 120,0 71 18NOV7b 11NOV7& -7.0 17MAR77 10MAR77 -7.0 141 255 GUVT APPROV HOSP & MISC EOliiP 30.0 71 22NOV7b 1DEC7b 9,0 2tOEC7b ~00Er.7b '1.0 230 q30 DELIVER PAINT MAlLS qS,O 71 2DEC7b 20MAA77 108,0 15jAN77 3MAY77 lOti.O b15 b20 R o.o 71 110EC7b 1MAY77 141.0 11DEC7b 1MAY77 1ql,O b15 &50 A o.o 71 110EC7b 2bJUL77 227.0 11DEC7b ?bJUL77 227.0 255 qqo DELIVER HOSPITAL & MISC EOUIP 180.0 71 22DEC7b 31DEC7& 9.0 19JUN77 28JUN77 9,0 EARLY START SORT Wt:r:l ABBREVIATED HERE ~~"d~ > ~ -1:' ()Q ~ Vl FIGURE 36 CONT. 001 0\~ I .!:' I~M PROJECT CONTROL SYSTEM RUN DATE 28 OCT 1b • • S C H E D U L E R E P 0 R T • • DATA DATE lB OCT 7& RUtl SEQUENCE 0 NETWORK ID 111 DA OISPENSARY•LACKLANO AFB TX MONTEDON CONSN FROto4 JUL 1fl TO SEP 77 PAGE SEQUENCE L S TOT S T A H T START F I N l S H FINLATE FLOAT EARLY LATE FLOAT (I l ( J) D E S C R I P T 1 0 N DURAT CAL EARLY 5 NTP 1.0 71 1JUL7b A 1JUL7b 0.0 1JUL7& A 1JUL7& o.o '5 '55 SUB SH DWGS ALUM ENTR & MTL DOORS 29.0 71 2JUL7b A 2JUL7b 0.0 30JUL7b A 30JUL7& o.o '5 80 SUBMIT ELECT FIXT & EQUIP 21.0 11 2JUL7b A 2JUL7b 0.0 28JUL7& A 28JUL7& o.o 5 90 SUB & APP SH OWGS REINF STL 2'5.0 71 2JUL7b A 2JUL7b 0.0 2&JUL7& A 2&JUL7& o.o '5 10 MOB S LAYOUT 9.0 71 4JUL7b A 4JUL7b 0.0 12JUL7& A 12JUL7& o.o 5 20 SUB & APP MECH & ELECT ROUGH•lN MTLS 31.0 11 5JUL7b A 5JUL7& 0.0 4AUG7& A 4AUG7& o.o 5 95 SUBMIT & APPROV ROOF OECK SH DWGS 4b.O 71 &JIIL7& A oJUL7& 0.0 20AUG7& A 20AUG7& o.o &JUL7& A &JUL7b 0.0 21JUL7b A 21JUL7& o.o '5 1'50 CONC DES MIX 1&.0 71 '5 bOO SUB ~ APP SH OWGS OUTSIDE ELEC & PLUMB 41.0 11 &JUL7b A bJUL7& 0.0 21AUG7& A 21AUG7& o.o 5 3'5 SUB SH DWGS STRUCT STL & JOISTS 30.0 71 9JUL7b A 9JUL7& 0.0 7AUG7& A 7AUG7& o.o A 9JUL7& 0.0 7AUG7& A 7AUG7& o.o '5 7'5 _SUBMIT PLUMB & MECH FIXT & EQUIP 30.0 11 9JUL7b "I 1-' '5 25 SUB SH DWGS PAN FORMS 21.0 7J 10JUL7b A 10JUL7& 0.0 30JUL7& A 30JUL7& o.o \0 5 40 SuB ~ APPRDV MASONRY MAlLS 4&.0 11 12JUL7b A 12JUL7& 0.0 2&AUG7& A 2&AUG7& o.o A 11AUG7& o.o 5 125 SUBMIT SH OWGS MILLWORK 31.0 11 12JUL7& A 12JUL7& 0.0 11AUG7& o.o 5 10'5 SUBMIT X•HAY PROTECTION &2.0 11 14JUL7b A 14JUL7& 0.0 13SEP7& A 13SEP7& 10 15 ROUGH GkAD & EXCAV BLDG 15.0 71 1bJUL7b A 1bJUL7b 0.0 30JUL7& A 30JUL7& o.o 1 0 &05 OEMOL ~ SITE GRADING 33.0 71 18JUL7& A 18JUL7& 0.0 19AUG7& A 19AUG7& o.o 20.0 71 21JUL7& A 21JUL7& 0.0 9AUG7& A 9AUG7& o.o 5 30 SUB SH OWGS METAL ODOR BUCKS 5 &5 SUB CERAMIC TILE 4&.0 71 2'5JUL7& A 25JUL7& 0.0 8SEP7& A 85EP7& o.o 0:, 110 SUBHtT & APPROV OOOH CANOPIES & SIGNS 45.0 71 2&JUL7& A ·?bJUL7& 0.0 8SEP7& A 85EP7& o.o 5 14~ SUBMIT HOSPITAL & MISC EQUIP 4'5. 0. 11 2&JUL7b A 2bJUL7b 0.0 8SEP7& A 8SEP7& o.o Wtrl 1-''"d c> ~ ()QI-'VI CXll 0\i-' I FIGURE 37 ~ Wt%:1 i-''"tj SEIIUFNCE L S PAGF 2 > c: .p. ()Q ,_. TOT S T A ~ T START F 1 N I S H FIN IJ1 001 (l) ( J) 0 E S C R I P T I U ~ OURAT CAL EARLY LATF FLUAT EARLY LATF FLOAT 0\i-' -----------------------------------------------------------------------------------------------------------------------I .p. 90 !50 DEL REINF STL 1q.o 71 27JUL7b A 27JUL7b 0.0 J4AIIG7b A 1 IIAUG7b o.o 80 ?15 GOV'T APPHOV ELECT FtxT & EOUIP 30.0 71 29JUL7b A ?9JUL7h 0.0 27AUG7& A .?7Al,G7b o.o 5 70 SURMJT TOILET PARTITIONS & ACCESSURIE~ 41.0 71 30JliL7b A 30Jlll7b 0.0 RSEP7b A 8SfP7b o.o 5 R5 SUR ~ APP SH DwGS MISC ~ETALS 31:>.0 71 30JUL 7b A 30JIJL 7& 0.0 3SfP7b A 3SEP7b o.o 15 !55 R o.o 71 30JUL7b A ~OJUL7b 0.0 30JIIL7b A 30Jlll7b o.o 15 2&':1 R o.o 71 30JUL7b A 30JUL7b 0.0 30JUL7b A 30JUL7& o.o 5 145 SURMIT tiiSC IILOu EQUIP 35.0 71 31JUL7b A 3JJUL7b 0.0 3SEP7b A 3SEP7b o.o 55 lqO GOV'T APPROV ALUM E~TR & MTL UO~RS t"i.n 11 31JUL7b A 3JJUL7b 0.0 14AIJG7h A 14AUG7b o.o 5 f>O SUR LATH & PLASTER 46.0 71 IIAUG7b A 4AU~7b 0.0 J8SEP7b A 16SEP7& o.o 5 120 SUBMIT VINYL wALL COVERI~G 31.0 71 4AUG7b A IIAUG7f. 0.0 3SFP7& A 3SEP7b o.o 25 thO GOV'T APPHOV PAN FO~MS 1&.0 71 4AUG7b A 4AUG7& 0.0 19AUG7b A t9AUG7b o.u " I ...., 20 !55 DEL MECH & ELECT ~OUGH•IN MTLS INITI'L 10.0 71 5AU&76 A 5AUG7b 0.0 14AIIG7& A 14AUG7b o.o 0 75 210 GOV 1 T APP~OV PLUMd & MECH FIXT & EQUIP 29.0 71 7AUG7b A 7AUG7b 0.0 IISfP7b A 4SEP7b o.o 35 170 Gnv•T APP~OV STR STL &JSTS 18.0 71 8AIIG7b A !lAIIG7& 0.0 2'5AIIG7b A ?'5Aut;7b o.o 30 1b5 GOV'T APPROV MTL OR BUCKS 12.0 71 10AIIG7b A IOAUG7b 0.0 21AUG7b A 21AUG7b o.o 5 tOO SUBMIT ~OOF ~ SHfETMETAL ~HOP D~GS 31.0 71 IIALIG7& A IIAUG7~ 0.0 105EP7& A 10SEP7b o.o 125 ?4U GOV'T APP~OV MILL~ORK 111.0 71 12AUG7b A 12AUG7b 0.0 25AUG7b A ?5AUt;76 o.o 5 13~ SUHMIT SH Ow~S CASf~ORK 11&.0 71 14AlJG7b A 14AU~7b 0.0 2ASEP7b A ?8SEP7b o.o 150 2f>5 R o.o 7t J4AUG7b A I4AUG7& 0.0 J4AUG7& A 14A1Jt;7f> o.o ~ 150 ?75 R o.o 7J 14AUG7b A JIIAU~7f> 0.0 14AUG7& A 14AUG76 0.0 150 biO H o.o 71 I 4AUG7f> ~ I 0.0 190 345 FAR & OfL ALUM ENTR ~ MTL DRS 90.0 71 J4AIIG7b A JIIAUf.76 0.0 11NOV7b 10MAR77 119.0 2&S 270 FTG~ ~ PLINTH~ 15.0 71 14AUC7b A I0 31~ DELIVER PAN FOUMS 53.0 71 19AUG7b A l9AUG7b 0.0 l00CT7b A IOOCT7b o.o b05 &10 A o.o 71 l9AIIG7b A 19AIJ(;7b 0.0 19AUG7b A 19lur.7b o.o 1>05 &12 R o.o 71 19AUG7b A 19AUG7b 0.0 1qlliG7b A 1qAIIG7b o.o 5 330 PWf-QUALIFY WELDERS 89.0 71 20AllG7h A ?OAIJG7b 0.0 lf>NOV7b 290EC7b 43.0 95 3~0 OELIVER RQOF DECK MAlLS 85.0 71 20AUG7b A ?OAIIG7b 0.0 12~0V7b 8JA~77 57.0 5 130 SUBMIT UESILIENT FLOOR SAMPLES .H.O 71 21AIIG7b A L'1AUG7& 0.0 20SEP7b A ~OSEP76 o.o 1b5 3?5 fAR ~ DELIVER MTL OR BUCKS 90.0 71 2lAUG7b A ?lAUG7& 0.0 1ANOV7b ?40EC7b 3b.O bOO ~12 DEL MAlLS OS ELEC ~ PLUMB 311.0 71 21AUG7b A L'1AUG7b 0.0 23SEP7b ~ 23SEP7b o.o 170 3?5 fAR ~ DEL STL COLS '>1.0 71 25AllG7b A ?5Aur.7b 0.0 1110CT7b A 140CT7b o.o 17 0 310 FAR ~ DEL STR STL ~ JSTS 90.0 71 25AUG7b A ?5AUG7b 0.0 22NOV7b ?90EC7b 37.0 ...... NI 2110 llh5 FAR ~ DELIVER MILLWORK 120.0 71 25AUG7b A 2~AUG7& 0.0 2?DfC7b 12JU~77 17t?.O ...... 110 175 DELIVER MAS0NRY MATLS 80.0 71 2bAUG7o A ?bAIJG7b 0.0 13NOV7b 22JAN77 70.0 275 ?RO RAS~T FND, SLAR, ~MS 17.0 71 2bAU&7b A 2~AUG7b 0.0 11SEP7b A 11SEP7b 0.0 215 1150 D~LIV~U ELECT FIVT & EQ~IP 120.0 71 ~7AIIG76 A ?7AUG7h 0.0 24DEC7b IIIJUN77 172.0 120 235 GUV'T Af'PtWV COLO~ :iEL VINYL o'4ALL CUVERINI.i 1S.O 71 4SEP7b A 4SEP7b 0.0 18SEP7b A 18SEP7b " u.o 4SEP7b 0.0 2RSEP7b A ?~SEP7b 0.0 1115 2b0 GOV'l APPROV HISC BLDG EQUIP 25.0 71 4SEP7b A 210 11110 OE.LIVER PLllriR & ME.CH EQUIP & FlO 1'>0.0 71 IISEP7b A IISEP7b 0.0 31JAN77 l7MAY77 10o.O 8'> 305 FAR & OELIVER MJSC METALS llh.O 71 ASEP7b A HStP7h 0.0 231lCT7b A ?30CT7b u.o &5 200 GOV'T APPROV CE~ TILE & COLUP. SEL 25.0 71 9~FP7h A 9SEP7b 0.0 30CT7b A 30CT7b o.o Wl:'%j ...... "'d > !=: ,1:" ()Q ..... V1 001 0\ ...... I ,1:"- 1-IGUPE 37 CONT. Wt%1 1-'"tt > c:: .~:" SEtlUE i~CF" L 5 PAGE 4 ()Q ...... V1 -----------------------------------------------------------------------------------------------------------------------001 TOT S T A H T START F I N I 5 H FIN 0\ ...... I (I) (J) 0 t S C ~ I P T 1 0 t~ OulhT CAL EAHLY LATE FLOAT EARLY LATE FLOAT .~:" -------------------·-------------------------------------------------------------------------------------------------- 711 205 GUll' T APPRLI\1 TOIL PART & ACCES 22.0 71 10SEP7b A 10SEP7b 0.0 10CT7b A 10CT7b o.o t Otl ~;>u r.ov' T APPI0 111"i Gli\1 1 T Af'Pi~S HARO·~•i-lf 30.0 71 190CT7b A 190CT7b 0.0 17N0117b 10NOV7b -7.0 310 3\ 'j 30X llfiPt< F Lk •'lt:CH ~ F.LECT f<-I ~o.o 11 20UCT7b A 200CT7h 0.0 IH~OV7b 4NOV7b -4.0 I 3t> J.0 71 71 71 71 71 71 71 71 71 71 71 71 71 71 7l 71 71 71 71 11 71 71 71 9NDV7b 9f'.lOV7b 18NOV7b c80CT7& 22NOV7b 280CT7b 28DEC7b 29DEC7b 3JAN77 220EC7b 1:SHIII77 280CT7b 25JA1'.77 141110V7b 2JAN77 3JAN77 290EC7b 2bJAN77 280CT7b 290EC7b 290EC7b 280CT7b 15FEB7 7 5NOV7b 5NOV7b 11NOV7fo 22NOV7b 1DEC7b 12DEC7b 24DEC7b 2SDEC7b 30DEC7b 31DEC7b 9JAN77 15JAN77 21JAN77 2 3JAN77 24JAN77 25JAN77 28J Alll77 28JAN77 1FEB77 4FE877 7FEB77 \OFE877 11FES77 • 4.0 • 4.0 •1.0 25.0 q.o 45.0 ·4.0 •4.0 •4.0 9.0 ·4.0 1q.o ·4.0 70.0 22.0 22.0 30.0 2.0 'lb.O 37.0 40.0 105.0 ·4.0 28DEC7b 28DEC7b 17MAA77 2bD£C7b 21DEC7b t0JAIII77 211DEC7b 2JAN77 t2JAN77 1qJUN77 211JAN77 bNOV7b t4FE877 1'5NDV7b 2JAN77 5JAN77 8MAA77 8FEB77 25JAN77 1MAA77 15JAN77 2bMAA77 11APA77 240EC7b 24DEC7b 10MA~77 L'OJAN77 300EC7b L'4FE877 240EC7f> 290EC1f> 8JAN77 28JUN77 20JAN77 24JAN77 IOFER77 24JAN77 ?4JAN77 27JAN77 7APA77 10FE877 lMAY77 7APR77 24FEB 77 9JUL 77 7APA77 •4.0 -4.0 -7.0 25.0 q.o 45.0 -4.0 -4.0 -4.0 9.0 -4.0 7q.o -4.0 7o.o 22.0 22.0 30.0 i:!.O 9&.0 37.0 40.0 105.0 •4.0 LAT~ START SOR1 ABB~tEVIATED HEFE wt:rl 1-'"tj > ~ ~ OQ I-' V1 col 0\f--o ~ FIGUP.E ~7 cmn. l~M PROJtCT CONTROL SYSTEM 7& S C H E 0 U L E R f P 0 R T DATA DATE 28 OCT 7& RUN OATF 28 OCT * * RLW SEflllENCE 0 NETwORK 10 Itt OA OISPENSARY-LACKLA~O Af8 TX MOHTEOON CONSR FROM JUL 7& TO SEP 71 * * -~=~~=~==--~-~:------------------------------------------~;~-----------;-~-~-~-~-------;;;~~----;-;~~~;-;-~-:_____ ;;~~ (I) (JJ 0 E S C R I P T I 0 N DURAl CAL EARLY LATE fLOAT EARLY LATE FLOAT 50 t85 GOV'T APPROV 8LORS HARDWARE lO.O 7t 1qOCT7& A tqOCT7b 0.0 17NOV7b 1ONOV7& -7.0 120.0 71 18NOV7b ltNOV7& •7.0 t7MAR77 ! OMAR77 -7.0 185 345 DELIVER BLDRS HARDWARE 18~AR77 ltMAR77 •7.0 JIMAR77 ?4MAR77 -7.0 345 385 INST MTL DRS ~ ALUM ENTR t4.0 71 385 3q0 STUCCO 14.0 71 tAPR77 ?.5MAR77 ·7.0 14APR77 7APR77 -7.0 3qo 3Q5 R o.o 71 14APR77 7APR77 •7.0 14APIH7 7APR77 -7.0 3q5 410 CEILG SUSP SYST ' INSUL 14.0 71 15APR77 HAPR77 -7.0 28APR77 2tAPR77 -7.0 410 430 PUS CLG 12.0 71 2qAPR77 22APR77 •7 .0 I OMAy77 ]MAY77 -7.0 QMA Y7 7 •7.0 7JUN77 3tMAY77 -7.0 Q"i.O 71 8JUN77 tJUN77 •7.0 22JUL77 15JUL77 -7.0 430 445 ~OX PAINT ~ FINISH 211.0 71 t1MAY77 445 505 50X COMP PAI~T & FIN I bJUL 71 -7.0 QAIIG77 ?AUG77 -7.0 505 510 20X PAINT & FINISH 18.0 71 23JUL77 7.0 71 10AUG77 3AUG77 -7.0 I&ALIG77 qAUG77 -7.0 510 &55 CLEAN•IlP BLDG ...... 5.0 71 17AUG77 IOAuG77 •7. (I 21 AllG77 54 1UUr.77 -7.0 ~I &55 bbO SELL JOB N 0.0 8NDV7& IINOV7b -4.0 IJI 310 315 JOl UNPR FLR MECH & FLECT R-I 20.0 71 200CT7& A 200CT7& ~o.o 71 qNOV7b SNOV7b -4.0 28DEC7b 24DEC7f> -4.0 315 320 FPC PAN SLABS & B~S qNOV7& 5NOV7b -4.0 2110EC7b 240EC7f! -4.0 315 325 701 llf~OR FLR MEC'i & ELECT R-I so.o 71 o.o 71 28DEC7b 24DE.C7b -4.0 28DEC7& 240EC7b -11.0 320 325 R 2qOEC7b 250EC7b •4.0 2JAN77 ?qOEC7& -4.0 325 330 ERECT STL COLS & METAL BUCKS 5.0 71 330 350 ERECT STR STL & JOISTS 10.0 71 3JAN77 30DEC7b •4.0 12JAN77 8JAN77 -4.0 ROOF OF.CK 12.0 71 13JAN77 qJAN77 •4.0 24JI.N77 20JAN77 -11.0 350 355 MTL 21. (I 71 25JAN77 21.JAN77 -4.0 tiiFEii77 I OFER77 -4.0 355 3&5 ROOFING ~ SHT 3&5 3q5 AC DUCTWORK 51>.0 71 15FEB77 11FEB77 ·4.0 11APR77 7APR77 -4.0 wt: c: """ (]Q ...... TOT S T A R T START F I N I S H FIN VI (I l (J) 0 E ~ C R I P T I 0 ~ OtlRAT CAL EARLY LATE FLOAT FARLY LATE FLOAT 001 0'11-' ---------------------;-------------------------------------------------------------------------------------------------I 390 405 R 405 420 CERAMIC TILE 420 430 R 1110 1111~ •cOuTST ~ OTHER CEILINGS 5 NTP 5 10 ~OR ~ LAYOUT 5 20 SUR ~ APP MECrl & ELECT ROUGH-IN MTLS 5 ?5 SU~ SH ONGS PAN FORMS 5 30 SUI3 SH uNGS ~ETAL DOOR llllCKS 5 35 SUB SH OwGS STRUCT STL & JOISTS 5 40 SUR ~ APPROV ~ASONRY MAlLS -...! I N ') 115 SUR SH u~GS MTL ~INOOwS 0'1 5 So SUR LIST & SAMPLES IILORS kARONARE 5 'l5 SUR Sti o.~GS ALIJM EIIITR A 114TL DOO~S 5 &o SUR LATH & PLASTF.K 5 &5 SUR rERA~lC TILE 5 70 SURMIT TOILET PARTITIONS A ACCFSS~RIF5 '5 7':1 5URMTT PLU"11:l & MECH FpT & Ell:JTI' '5 80 SUI3MTT ELECT FIXT & ffllliP '5 B5 SUA ~ APP SH ONGS MlSC METALS 5 90 SUB ~ APP SH ONGS REINF STL 'i Q'j SUAMIT & APPQOV QOOF OfCK Srl 0~GS '5 100 SU~MIT HOOF ~ SrlEET~FTAL SHOP DNGS """ o.o 71 14APR77 11APR77 -3.0 14APR77 11APA77 -3.0 2?.0 71 15APR77 12APR77 ·3.0 6MAY77 3MAY77 -3.0 o.o 71 bV.AY77 3MAY77 •3.0 6MAY77 31o4AY77 -3.0 35.0 71 29APR77 27APR77 -2.0 2JUN77 31MAY77 -2.0 1.0 71 IJUL7b A 1JUL7& 0.0 1JUL7& A 1JUL7& o.o 9.0 71 4JUL7b A IIJUL7b 0.0 12JUL7& A 12JUL76 o.o 31.0 71 5JilL7b A 5JUL7& 0.0 4AUG7& A 4AUG76 o.o 21.0 71 10JUL7b A IOJUL7& 0.0 30JUL7& A 30JUL76 o.o 20.0 71 21JUL7b A 21JUL7& 0.0 9AUG7& A 9AUG76 o.o 30.0 71 9JilL7& A 9JUL76 0.0 7AUG7& A 7AUG76 o.o 111>.0 71 12JUL7b A 12JUL7& 0.0 2&AUG76 A 26AUG76 o.o 311.0 71 17AIIG7b A 17AUG7b 0.0 19SEP7& A 19SFP76 0 •.o b'5.0 71 15AUG7b A 1SAUG76 0.0 180CT76 A 180CT76 o.o 29.0 71 ?JUL7b A 2JUL7b 0.0 30JUL76 A 30JUL7b o.o 11&.0 71 4AUG7b A IIAUG76 0.0 18SEP7b A 18SEP76 o.o 11&.0 71 25JIJL7b A 25JUL7& 0.0 ASEP7& A 8SEP7& o.o qi.O 71 10JIIL 7b A 30JUL 76 0.0 ASEP7b A 8SEP76 o.o 30.0 71 9JUL7b A 9JUL7b 0.0 7AUG7b A 7AUG76 o.o 27.0 71 2JUL7b A 2JUL7& 0.0 28JUL7b A 28JUL7b o.o Jb.O 71 30JUL7b A 30JUL7b 0.0 ~SEP7b A 3SEP7b o.o 2'5.1) 71 2JUL7b A 2JUL76 0.0 2&JUL7b A 2&JUL7& o.o 111,.0 71 bJUL7b A &JUL7b 0.0 20AUG7& A 20AUG7b o.o 31 • 0 7 I IIAUG7b A 11AUG7b 0.0 IOSEP7& A IOSEP7b o.o TOTAL FLOA'f SORT ABBREVIATED HERE FIGURE 33 corn. IR~ PROJECT CONTROL SYSTE~ I~II'J llA TF .?II OCT 7h * * Lu'-'P SliM COST REPORT * * DATA DATE 28 OCT 7f> RIHJ SEilllEIIICf 0 ~JETt~ORK lU Itt TJTLE OA DIS~f~SARY-L,CKLA~~ AF~ TX MONTEDON CONSR FROM 1 JUL 7ft TO 1 SEP 77 PAGE SEI,Ufi'ICE L F ORGANIZH 10·~ ,.. I START I .o J ?ooo. zooo.' ftJ UL 7fo .o 100.00 A 21JUL7b • o J o. o • 1~11 co~c DES "'I• "5 qo Srr!1 '-APP Sli OwGS REI NF 'A 2JUL7fo .o 100.00 A ~bJUL7b .o J o. o. STL on FLECT FIXT II. EQUIP A o?JUL7b .o 100.00 A o?8JIJL7b .o J o. o. '5 Sllt:II~IT '5 ~5 SIIB SH OI"'GS PAN FORMS A 10JllL7b .o 100.00 A 30JUL7b .o J o. o. '55 SIIB SH Ot~r.S ALIJM I'NTR II. MTL DOORS A o?JIJL7b .o 100.00 A 30JIIL7b .o J o. o. " ~ EXCAV RLOG A lf>JIJL.7b .o 100.(10 A 30JUL7b • o 1 11000. 11000 • tu 15 ~nur.H GRAO 1~'5 i( A 30JIJL7b .o 100.00 A 30JUL7& .o t o. o. A 30JUL7b .o 1no.oo A 30JIJL"7b .o 1 o. o. \5 ?t.<; k o. o. '" SUB & APP MFCH , ELECT ROIIGH-IN MTL<; A '5JIJL7b .o 1no.oo A IIAUG7b .o 1"> 20 o. SH OI"'GS STRIJCT STL ~ JOISTS A QJIIL7b .o tno.oo • 7AIJG7b .o 1 o. 5 35 SUS c; 75 SllB"'lT PLII·"'~ , "~ECH FIXT P. EtlliiP A QJrJL 7b .o 100.00 A 7AUG7b .o 1 o. o. 5 30 SUB SH D~G5 METAL ODOR RUCKS A o?tJUL7b .o 100.00 A QAUG7b • 0 J o. o. 5 teo; SUBMIT SH OI"'GS ~ILLWORK A 12JUL7b .o 100.00 A 11 AIJG7b .o t o. o. 20 l'jS OEL MFCH K ELECT ROUGH•IN MTLS T~TTIAL A '5t.Ur.7b .o 100.00 A 111AUG7b .o t 13000. 13000. -.1 .o t o • o. .,.. & MTL OJO~S A 31JIJL7b .o 1ou.oo A 111AUG7b A 27JUL7b .o 100.00 A 111AIJG7b • o 1 qooo • 9000. I \90 GOV 1 T APPROV 4LIIM ENTR N Ql) ISO DEL REINF STL ·o. -.1 1'SO 2b'5 R A 111AIJG7b .o 100.00 A 111AUG7b .o J o. A 14AUG7b .o \00.00 A 111AUG7b • o 1 o. o • 150 27'5 k 1"i0 &10 R A IIIAIJG7b .o too.oo A 111AUG7b .o 1 o. o. 10 &0'5 OEMOL ~ SITE GRADING A 18JUL7b .o 100.00 A 1qAIJG7b • 0 I tnooo. 10000. &OV'T AP~ROV PAN FORMS A IIAUG7b .o too.oo A 1QAIJG7b • o J o. o • lbO A \qAIJG7b .o 1no.oo A 1QAUG7b .o I o. o. o • toO'S"" 1>10 R A 1QAUG7b .o 1no.oo A 19AIIG7b • o I o. hil'i bl? R A bJUL7b .o 1(10.00 A o?OAIJG7b • o J o. o • "> 95 SIJBMIT & APP~OV KOllF DECK SH Ot~GS \\ 'S bOO Slltl II. AP~ S~ OwGS UIJTSIOE t.U:C II. PLIIMR A bJIIL7b .o 100.00 A o?IAUG7b • o I o • o. 30 1&'5 GOV'T APPROV MTL OK BIJCKS A 10AllG7b .o too.oo A o?\ALIG7b • o J o. o • 55 17 0 GOV'T APPROV STR STL &JSTS A IIAtJG7b .o 100.00 A 2'5AUG7b .o I o. o. 125 ?<10 &OV'T APPRUV MILLWORK A 12AUG7b .o 100.00 A 2'5AUG7b • 0 I o. o • o • ., (10 Slltl & APr>ROV "'ASUNiH MAlLS A 1?JIJL7b .o too.oo A 2bAIJG7b • o I o. I'S5 ;n5 kOUf.H-PI IINOEW liS'-'T A 1'5AUG7b .o 100.00 A o?bAUG7b .o J 2000. 2000. 1\(l i't5 ~OV'T APPRIIV ELFCT FIXT ~ EgiJJP A o?QJUL7b .o 100.00 A o?7AIIG7b .o J o. o. ?h5 ?70 FTGS II. PLPc .p.. 1"> ?tn GOV'T APPRtlV PLLJMR OQ I-'., b') Sllh CFf.>A~Il( TILF A 2'5JUL7b .o 1no.oo 8SEP7b .0 I o. o. \J1 .o \00.00 •' 8SEP7b • 0 I o. o• CXl I ') 70 Sllb'41 T TlllLI'T PAIH IT IOI1 PAGE 2 ,..........., ~ -......! r N 00 5 5 '5 275 5 '5 5 120 '5 5 &00 '5 100 Ill'S ':i 70 280 bO b'i 45 2(15 IuS 270 300 lbO 130 170 5 11'5 3l10 6JUL7b .o 100.00 A 8SEP7& .o I o. o. r 140 SUB~IT HOSPITAL & MISC f~UIP A 2bJUL7b .o 100.00 A 8SEP7& • 0 .p- I o. o. 100 SIIRMIT ROOF & SHEFTMETAL SHOP OwGS A 11AIJG7b .o 100.00 A 10SEP7& • 0 I o. o. 280 BASMT FNO, SLAB, RMS A 2f>AUG7b .o 100.00 A 11SEP7& .0 I ~ooo. JOOO. 10'5 SUBMIT X-RAY PROTECTION A 111JUL7& .o 100.00 A 13SEP7& .o I o. o. &0 SUB LATH & PLASTER A 4AUG7& • o 100.00 A 18SFP7b • 0 I o. o • I 1'5 SII8MIT PAIIH SAMPLES A 19AUG7& .o 100.00 A 18SEP7& .o I o. o. 23'5 GOV'T APPROV COLOR SEL VINYL wALL COVERING A 4S~P7& .o 100.00 A 18SfP7b .0 I o. o. 11'5 SIJil SH OiiGS MTL iiTNflOwS A 17AUG7& .o 100.00 A t9SEP7& .0 I o. I 50 SlltSMI T •H.SILifNT FLOOR SU4PLES A 2UUG7b .o 100.00 A 20SEP7& .0 I "·o. o. &12 OEL MATLS OS fLFC & PLUMS A 21AUG7& .o 100.00 A 23SEP7b .o I o. o. 13'5 SURMIT SH O~GS CASEWORK A 14AIJG7& .o 100~00 A 28SEP7& .o I o. o. 220 GOV'T APPROV ROOF & SHMTL SH ONGS A IISEP7& .o 100.00 A 28SEP7b .0 I o. o. 2b0 _GOI/'lAf>PRUV MISC BLDG EQUIP A IISEP7& .o 100.00 A 2~SEP7& .o I o. o. 157 C.O. TO USE SOM~ GUV FURN HOSP EQUIP A 28SEP7b .o 100.00 A 28SEP7b .0 I o. o. 20'5 GOV'T APPROV TOTL PART & ACCES A 10SEP7& .o 100.00 A IOCT7b .0 I o. o. 2d'i BASMT wALLS A 12SEP7& • o 100.00 A i'OCT'b .o I 4'500. 11'500 • 19'5 GOV'T APPROV LATH & PLASTER A 19SEP7& .o 100.00 A 30CT7b .o I o. o. 200 GOV'T APP~OV CER TILE & COLO~ SEL A 95EP7& .o 100.00 A JOCT7& .o I o. o. 180 GOV'T APPROV MTL WINDOwS A 20SEP7& .o 100..00 A 40CT7& .o I o. o. 300 DHIPPRllOFINt; A ."50CT7b A &OCT7b .o 100.00 • 0 I 1'500. 1500. 2c'5 GOV'T APPROV X-RAY PROTECT A 14SEP7& .o 100.00 A 80CT7b .0 I o. o. 300 GRAOE BEAMS A 295EP7b .o 100.00 A 80CT7& .o I 10000. 10000. 30'5 ~ A 80CT7b .o 100.00 A 80CT7& .o I o. o. 31'5 DfLTVEH PAN FO~MS A 19AIIG7b .o 100.00 A 100CT7b .o I o. o. 211'5 GOV 1 T APPROV & COLOR SEL RESILIENT FLOOR A 21SEP7b .o 100.00 A 130CT7b .o I o. o. 32'5 FAO ~ DEL STL COLS A 2'5AUG7b • o 100.00 A 1110CT7& .o I 1'500. 1'500 • 50 SU~ LI~T & SAMPLES RLD~S ~ARUWARE A 1'5AUG7& .o 100.00 A 180CT7b .o J o. o. 11h GOVT TEST & OISAPP~OV PAINT A 19SF.:P7& .o 100.00 A 180CT7b .o I o. o. liO F&B & GRADE UNDER ~LOG A 90C 17b .o 100.00 A 200CT7b .o I 4'500. 11'500. l0'5 FAB & DELIVER MISC METALS A ASEP7b .o 100.00 A 230CT7b • 0 I 3500. 3500. 13A NEGO c.o. '' A 29SEP7b • o 100.00 A 230CT7b .o I o • o. Hill R A 2JUCT7b .o 100.00 A 230CT7b .o J o. o. 250 GOV'T APPROV CASEwORK A 29SEP7b .o 100.00 A c&OCT7& .0 I o. o. 31~ 30% U~PR FLR MEC~ ~ ELECT H-I A 200CT7b 12.0 39.99 11NOV7b .o I 11800. 4130. ~~~ GOV'T APPROV ~LOHS ~ARUWARE A 190CT7& 21.0 ?9.99 10NOV7b .o I o. o. 1<11 RE!>IJB rlOSP II, MISC EfluiP A 2'IOCT7& 25.0 t&.bf> 30NOV7& • 0 I o. o. 1~~ FAR II, DELIV~R MTL OR BUCKS A 21AIJG7b 22.0 75.5'5 211DEC7b .o I ?000. 1480. 1~0 FPC PAN SLA~S ~ ~MS 9t~OV7b 50.0 .o 240EC7& -11.0 I 17500. o. 32S 70% UNOR FLR ME~~ \ ELEr.T R-1 9NOV7b 5u.o .o c11DEC7& -4.0 I 27000. o. FIGURE 39 CONT. IRM PPilJECT CONTROL SYS}E14 RUN OATf l~ OCT 7h * * LllMP SLIM COST REPORT OATA DATE ?b OCT 7& * * RIW SEflii[IIICE 0 llllT~ORK TO II\ TITL£ OA OISPENSARY-LACKLAIIIO &FB TX ~ONTEDOIII CONSR FROM JUL 7& TO I SEP 77 SErHIENCE L F O~r.AIIII H TI or~ f'AGf 3 ~ I START HEMAl PERCNT FINISH ESTJM 0 ACTUAL~Jl 0 E ~ r q T P T T 0 N OATE DliRAT cor~PL T OATE FLOAT COST ClJST T-O -----------------------------------------------------------------------------------------~------------------------------ 320 1c?"i H 280EC7b .o .o 2l!.DEC7b -4.0 I o. o. 5 HO PRE-IWAL [FY ~ELOERS A c?OAIJG7b e»o.o H.B 290EC7b .o J o. o. 170 "HO FAd & lJEL ST" STL & JSTS A 25AlJG7b 2&.0 71.11 29DEC7b .o I 19000. 13300.325 HO ERECT ~TL C0LS ~ METAL BUCKS 29DEC7b '5.0 .o 29DEC7b -4.0 J 1000. o.1411 ?55 GOyT APP~OV HOSP ' MISC EflUTP 221110117& 30.0 .o 300EC7b 9.0 J o. 0. 9~ 350 UELTYFR ROUF DECK MATLS A 20AUG7b 1b.O llb.bb 8JAN77 .0 J o. o. 330 "JSI) ERECT ST~ STL ~ JOISTS 'IJAN77 to.o .o r.JAN77 -11.0 J :!1~00. o. 220 355 FAd.~ OFLIY SHHTL & ROOF 2~0CT1b bO.O • o 20JA11177 25.0 I o. o • 350 'IS<; ROOF Ot,CK 13JAIII77 12.0 .o 20JAN77 -4.0 T 9500. o. 410 172.22 22JAIII77 .o J 9'500. 7410.175 H5 SAMPLF 14ASUN~Y PANELS 1111~0117& 2.0 .o 211JAN77 70.0 I o. o.30'5 H<; BSMT STEPS \ LNOGS 2110CT7b 1o.o .o 24JAN77 79.0 I 900. o. HO H"\ H 2JA"l77 • o .o i'IIJAIII77 22.0 J o. o • 180 'lt>O FAR & DELIY€R METAL WINOO~S 2fiOCT7b 90.0 • o 27JA,..77 2.0 I i»OOO. o • -...,J BS 3b0 TIMF LAG I 3JAIH7 3.0 .o 27JAIII77 U.O I o. o. 35'5 3t><; ROOFING & SHT NTL 2SJAN77 N ?1.0 • o 10FEB77 -4.0 I 1bCIOO. o • \0 3b0 3b"i INST 14TL Wli\100.'15 2bJA.'l77 tll.u .o 10HB77 ?..0 J soo. o.11 b 1 1 7 RESIJIP-41 T PA I•H SAMI'LES A 1AllCT7b S.ll t>ll.bb 17FER77 .0 J o. o. i'2S 370 OfLIVER PPOTECT ~ATLS 28UCT1b 7'5.0 • o ?4FER77 45.0 I 3500. o • 320 370 CONC TOPPING FILL 290FC7o 18.0 .o 211FErl77 110.0 I ssoo. o.3bS '17 o R 111FER77 • o .o 211Ffb77 10.0 I o. o • 11i"> 3"<; DFLIYE~ ijLORS HARO•ARf 1fi1110V7b 1<'0.0 • o 10MAR77 -7.0 I 9000. o • IQO "5415 FAB ' OFL ALUM E~TR ~ NTL OQS A 111AIJG7b 1'5.0 ll:i.B 10MAR77 .0 J 11'500. 3&90.BS 3410 EXTf~IUR MSNRY WALLS 3JAl\J77 n.o • u 10MAR77 40.0 I 9500 • o.3110 141'; R 2'UAN77 • o .o 10MAR77 40.0 I o. o • 117 no RETEST ' APPROY PAINT ;)N0Y7b 30.0 • (i 19MAH77 1011.0 J o. o • IQ5 'ld"\ R 111FFII77 .u • o 211MAR77 311.0 I o. o • 320 37'5 ELErT kOur.H-IN 290EC7b b.5.0 • o 7APR77 37.0 J ;>OOOO. o • 320 MfC~ ~ ,qc; PLUM~ RUUGH•IN 29D£C7& 70.0 • o 7APR77 30.0 I 21000. o • :So5 H<; AC DUCT'iU~K I 20 OELTVFR ~ INSTALL STQPM ORAT~AGF 28llCT7b &o.o • o 1MAY77 12&.0 I 10000. o • (X) I-' Cl' l.n I 1-' I -'=' FIGURE 39 CONT. l~M PROJECT CONT~OL SYSTE~ RIHI l'lA TE 21\ OCT 7b I.•J'-'P Silo.! COST REPORT * * DATA OATE 28 OCT 7& * * Ru;~ SEQIJ[NCF 0 NET~O~K TO Ill TITLE OA OISPF~SARY•LACKL~NO AFB TX MONTEOON CONSR FROJ.~ JUL 7& TO 1 SEP 77 Wts:l 1-''"d SEQIIF~ICf L F flR(jANI14TION PAGE II :> ~ .p.. ()Q ..... ~ I START iiE"lA I PERCI~T FINISH ESTIM 0 ACTUAL UT CXl ~ rJI 0 E S C R I P T I 0 N DATE OURAT CO~PLT DATE FLOAT COST COST T-O 0\ ..... I ---------------------------------------------------------~~---------~----------------------------------------------------.p.. bli.' &15 OIITSIOE PLUM~ING 28liCT7b 45.0 • o 1MA Y7 7 141.0 J 7000. o • ol? f>l q OUTSIDE ELECTRICAL 28DCT7b CJo.o • o 1MAy77 CJ&.n I 24000. o • &15 f>20 K 110EC7b .o .o 1MAY77 141.0 J o. o. &JCJ &20 R 25JAN77 .o .o H1AY7 7 CJfi.O J o. o. 2~0 1130 OFLTVfR PAINT MATLS 20EC7b 45.0 .o 3MAY77 1011.0 J o • o. .J.(J 53.33 12JUN77 .o J 6000. 3120. 11115 llb5 R 7 JIJN1'7 .o .o I<'JU,.,77 s.o J o. o. &20 ,~c; SURr.RAOE & RASE FOR PAVING 2f>JAN77 42.0 .o li.'JUN77 CJf>.O J 13500. o. <.'15 450 OELTVF.:R ELECT FIXT & flliiiP A 27AIIG!b '58.0 51.&& 14JUN77 .o I 23000. ttson. 11115 ll'jO R 7JtJrH7 .o .o 111JUN77 7.0 J o. o. 11110 1155 R 10MAY77 .o .o 2f>JU"'77 117.0 T o. o. 1145 455 ~ 7JUN77 • o .o 2f>JUN77 19.0 I o • o. 2')5 490 DELIVER HOSPITAL & MISC EQUI~ ....... 220EC7b 180.0 .o 28JIJN77 CJ.o 1 23000. o. I llb5 1175 INST SOX MILLWURK 8JIIN77 1&.0 .o 28JU~J7 7 5.0 I 1500. o. w 1170 1180 RESTL FUI 0 I\JIJN77 21.0 .o 211JIJtl77 .o J l"iOO. o. 1175 1180 ~ 23JUN77 .o .o ~IIJUN77 5.0 J o. o.1180 1190 R 21\JIJN77 .o .o 2P.JIJN77 .o J o. o. 1 56 490 OEL TV GOVT FURoJ HOSP F!liiiP A 2~0CT7b 235.0 2.011 211JIJN77 .o 1 o. o. b25 b3ll CIIRR ~ GUTTF.R QMAR77 21.0 • o JJ•JL77 9&.0 J aono. o • 2')0 1185 DELIVER CASENORK 280CT7b l"iO.O .o 'IJUL77 10'5.0 I lf>OOO. o.IIIlO lin') k 21\JtH07 .o .o r,JifL 77 11 • 0 J o. o. 11115 "i05 50% COMP PATNT ~ FIN I\JIH~77 45.0 .o 15JUL77 -7. 0 J f>500. o. 117C. 'iO"i COMP "~ILL"'ORK 211JU,H7 lf>.O .o t5JUL77 &.o J 1500. o. 20') II~') DELIVER TOILET PART & ACCESS c?80CT7b CJo.o .o tbJUL77 172.0 I aooo. 0. 1120 II~S R f>J1AY 7 7 .o .o lf>JIJL 77 71.0 J o. o.235 lli>O DFLIVER VINYL WALL COVtRI~G 2110CT7b &o.o .o 1QJUL 71 ?05.0 I 1500. o.2b0 11~'5 DEL TVER ~ITSC BLOG ErltJIP 2110CT7b QO.O .o t'iJUL77 17'5.0 I f>OOO. o.11115 11&0 R 7JIIrl77 .o .o l'IJUL77 4?.0 I o. o. lldU IICJS R 211JUtH7 .o .o 1QJUL77 ?I • 0 J (1. o. 110 '500 OELIVFR DOOR CANUPifS & SIGNS 2110CT76 75.0 .o 2~JIJL 77 1'14.0 I ?000. o. FIGURE 39 CONT. I~M f'NOJECT CONT~OL SYSTEM RU'< IIATF ,!P. OCT 7u LllMf' SUM COST ~~PORT OATA DATE ?8 OCT 7b * * • * RUil St:'HilNCf 0 'H:.T.10~K IO ttl TTTLE llA f)J'\Pf~.0 l o. o. b30 ., 3"i i'1ALI(5 j0~1ArH7 21.0 .o 211JUL77 Qb.O I 11000. o. b so 1>4'5 ASPiiAL T t'Avl:;r, 30MA~77 ttl.O .(i 211JUL77 107.0 I 1>500. o. b~"> f>ll"i k tQAPi/77 .o .o 211JUL77 Qb.O I o. o. (1(10 b')O INST .,t:.r.h EflUIP I ti1AY77 70.0 .o 2bJ11L77 7.0 T 5ono. o. 11')0 bjO INST FLEC T F I WT ~ tlliilP ltJUN77 112.0 .o 26J11L77 7.0 I 3000. o. 115"> b51) INS T PL[11·18 ~ M[Cii F 1x T 8JtPH 7 30.0 .o 21>JIJL77 1Q.O I 2500. o. bl"l 1>50 k t10f.C7b .o .o 2f>JIJL77 ?27.0 I o. o. blq 1>')0 H 25JA·H7 • o .o 2f>J11L77 1112.0 l o. o • lli''S ";JI) TOILET PAkT 6 ACCESS HIAY 7 7 17.0 .o 2AUG77 71.0 I 700. o. llt>O '510 VINYL .dLL Cf1V~Q IIJUN77 111.0 .o 2A11&77 112.0 l 1000. o. 4/l(J "iiO 60V'T TEST x-~AY PkOTfCT 2QJIH.77 3.0 .o 2AUG77 32.0 I o. o. lib'S "itll IPJST CASfWO~I\ 2QJ1Jo~7 7 211.0 .o 2AUG77 11.0 I 3000. o. qqo "itO INST Jol()c;P II. ~1ISC flWIP 2QJIJN77 35.0 .o ?AUG77 .0 I 11000. o. -...! 49'5 <;tO INST MISC ~LOG E~UIP zqJ•J~77 111.0 .o ?AUG77 21 .o I 800. o. I w "iHO 'itO INST nunw CA~O~IES 11. S!~~s 51)JA'1177 10.0 .o 2A1JG77 17'5.0 I 500. o. ..... "iu'S "itO 20l PAl~! ~ FINISH 2~JUL77 18.0 .o ?A11G77 -7.0 I ?bOO. o. 5tt1 I,')'5 CL t:: All-UP tiLOG t0AUG77 7.0 .o 4UUG77 -7.0 I 1000. o. bll5 l)'j') TOP!IOIL ~ F io';E r.t')'5 TfST ~tCH ~ ELt::CT 20JIJL77 111.0 .o QAUG77 7.0 I 3000. o. b'S"i ~'>t>O SF.LL Jt1~ t7A•JG77 '5.11 .o 111AIIIj77-7.0 I 1000. o. ----------------------------------------------------~------------------------------------------------------------------- J fJ 1 A L 580000. 117&30. TOTAL PROJECT t:.STII1ATF.:U COST S ~110000. TnTAL PR~JtCT ACTUAL COST TO DATE S 1l7b30. E'IIO OF hEPO~T wt:r:j t-"1-d ~ < t; it~ CD ()Q t C/l l.n CD OOI 0\ ..... b:l I 1-' ~ Ill FIGURE 39 CONT. ~ EP 415-1-4 31 Aug 86 CHAPI'ER 8 SUMMARY Sumnm-y. '!he above information is intended as a basic introduction to Network Analysis. '!he figures are examples of the numerous programs which exist on the market. All such systems are dependent on high quality accurate input schedule information. Once that is obtained, valuable information can be extracted from the analysis data. Exanples have been included of management sorts which will have different value for different managers. Other sorts and presentations are available from various programs on the market. Each user mst determine what information he needs and specify only that which he requires. Techniques such as durlley supression and shortened versions of certain sorts are reconmended in order to limit the volume of paper in each report. Systems available allow the design of almost any kind of data arrangement desired. 'lhe reports, if based . on accurate data, will project completion and displa_y the causes of any dela_v. 'lhe manager can then use this information to decide on the most appropriate course of action available to him under the contract. NAS schedules, properly used, can be a definite aid in executing the Government's responsibilities under a contract and requiring the contractor to execute his responsibility. a. When the Work is Changed. It is very important that the logic diagrmn be revised to reflect any appropriate revision of logic, restraints, new activities, deleted activities, or revised durations and monetary values. With progress data posted as of the next update the impact of this change on the project can be evaluated. '!he determination of impact on time and money should be made concurrently; it must consider the status at the time the change is ordered; and it mst not be dela_ved for later determination. b. Time Scaled Diagrams. Network Diagrams, (Precedence or Arrow types), can be constructed to a horizontal scale of time. 'lhis procedure is favored by some who see benefit in the visibility, afforded by such a method. A vertical line representing the current date can be displayed and analysis made based on whether posted progress is left or right, of the line. 'lhis is often a good briefing or display technique on a summary diagram. Also numerous computer plotting systems are available which will generate time scaled and bar chart diagrams from the schedule information. 'lhese may be useful tools for display or briefing purposes, however basic information necessary for project management can be obtained from standard computer printouts as illustrated previously. ' 8-1 • U.S. (;UVIIUIIIfl/1 l'llllliii/G OfiiCF: 1993-352-b27/R0428